Rate analysis
Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete.
DSR rate₹585.70as per item analysis
Close fitting adjustable ridges
- Item code
- 12.12.3
- Sub-head
- SH 12 · ROOFING
- Unit
- See analysis
- Source row
- 633
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for length of ridge 20.2 metres Close fitting adjustable ridges | |||||
| Consider a shed of 20x10m (external dimensions at plinth). | |||||
| Length of ridges 20.2 metre | |||||
| No. of ridge pairs required, of length | |||||
| 1.22m each = 22.00 nos. + | |||||
| Add 5% wastage = 1.10 Nos. | |||||
| = 23.10 nos.x 1.22= 28.182 metre | |||||
| 0224 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement close fitting adjustable ridge. | metre | 28.182 | ₹230.00 | ₹6,481.86 |
| 9977 | Carriage | L.S. | 16.12 | ₹2.27 | ₹36.59 |
| 9999 | Sundries | L.S. | 7.15 | ₹2.27 | ₹16.23 |
| LABOUR | |||||
| 0130 | Mistry | day | 0.14 | ₹897.00 | ₹125.58 |
| 0112 | Carpenter 2nd class | day | 0.55 | ₹816.00 | ₹448.80 |
| 0114 | Beldar | day | 1.64 | ₹736.00 | ₹1,207.04 |
Rate build-up
| TOTAL | ₹8,316.10 |
| Add 1 % Water charges on "W" | ₹83.16 |
| TOTAL | ₹8,399.26 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,786.52 |
| TOTAL | ₹10,185.78 |
| Add 15% CPOH on "Y" | ₹1,527.87 |
| TOTAL | ₹11,713.65 |
| Add Cess @ 1% on "Z" | ₹117.14 |
| Cost of 20.20 metre | ₹11,830.79 |
| Cost of 1.00 metre | ₹585.68 |
| Say | ₹585.70 |