Rate analysis
Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.
DSR rate₹172.60per kg
In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
- Item code
- 10.25.2
- Sub-head
- SH 10 · STEEL WORK
- Unit
- kg
- Source row
- 1256
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of 1mx1m framed guard bar grating (0.218 quintal). | |||||
| MATERIAL | |||||
| (i) M.S. flat 50x6mm 2.4kg/per metre | |||||
| 5.75x2.40 = 13.8kg.+ | |||||
| Add wastage @ 5% = 0.69kg. | |||||
| Total = 14.49kg. Say 14.5 kg. | |||||
| 1008 | Flats upto 10 mm in thickness | quintal | 0.145 | ₹5,450.00 | ₹790.25 |
| (ii) 12mm dia. bars @ 0.89 kg/m | |||||
| 9x1= 9metre @ 0.89kg/m = 8.01kg+ | |||||
| Add wastage @ 5% = 0.40kg. | |||||
| Total = 8.41 kg. Say 0.084q | |||||
| 1002 | Mild steel round bar 12 mm dia and below | quintal | 0.084 | ₹5,550.00 | ₹466.20 |
| 2205 | Carriage of Steel | tonne | 0.023 | ₹0.00 | ₹0.00 |
| 1215 | Welding by electric plant 60 cm | cm | 60 | ₹2.50 | ₹150.00 |
| LABOUR | |||||
| 0102 | Blacksmith 1st class | day | 0.7 | ₹897.00 | ₹627.90 |
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| 0100 | Bandhani | day | 0.25 | ₹816.00 | ₹204.00 |
| Applying priming coat 0.6 sqm. | |||||
| 13.50.3 | Rate as per item no 13.50.3 of SH : Finishing | sqm | 0.6 | ₹67.40 | ₹40.44 |
| 9999 | Sundries | L.S. | 4.55 | ₹2.27 | ₹10.33 |
Rate build-up
| TOTAL | ₹2,657.12 |
| Add 1 % Water charges on "W-A" | ₹26.17 |
| TOTAL | ₹2,683.29 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹562.13 |
| TOTAL | ₹3,245.42 |
| Add 15% CPOH on "Y-A" | ₹480.75 |
| TOTAL | ₹3,726.17 |
| Add Cess @ 1% on "Z-A" | ₹36.86 |
| Cost of 0.218 qunital | ₹3,763.03 |
| Cost per kg | ₹172.62 |
| Say | ₹172.60 |