DSR 2023 · SH 10 · STEEL WORK

CPWD DSR item 10.25.1 rate analysis

Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete

Published rate₹123.60per kg
Rate analysis

Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.

DSR rate₹123.60per kg

In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete

Item code
10.25.1
Sub-head
SH 10 · STEEL WORK
Unit
kg
Source row
1256

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 5.331 quintal
Consider a flight of staircase of 2.8m height with tread and riser of 200mm & 0.60m wide.
MATERIAL
(i) Unequal angles as stringers-75x50x6mm
4x12.69x5.6 = 284.25 Kg.
Add wastage @ 5% = 14.21 Kg.
Total = 298.46kg. Say 2.985q
(ii) unequal angles at sides -50x30x5mm
2x14x0.2x3.00=16.8kg.
Add wastage @ 5% = 0.84kg.
Total = 17.64 kg. Say 0.176q
Total = 3.161q
1007 Structurals such as tees,angles channels and R.S. joists quintal 3.161 ₹5,965.00 ₹18,855.37
(iii) plate for tread 8mm thick
14x7.5 = 105.00kg+
Add wastage @ 5% = 5.25kg.
Total = 110.25kg. Say 1.103q
1010 Mild steel plates quintal 1.103 ₹5,700.00 ₹6,287.10
(iv) G.I. pipe for rolling 40mm
2x12.69m = 25.38m+
Add wastage @ 5% = 1.27m
Total = 26.65m
1549 G.I. pipes 40 mm dia metre 26.65 ₹290.00 ₹7,728.50
(v) M.S. round bars 16mm dia.
15x0.75x2x1.58 = 35.55kg.+
Add wastage @ 5% = 1.78kg.
Total = 37.33 Kg. Say 0.373q
1003 Mild steel round bar above 12 mm dia quintal 0.373 ₹5,450.00 ₹2,032.85
2205 Carriage of Steel tonne 0.464 ₹0.00 ₹0.00
(3.I61 + 1.103+0.373)=4.637q = 0.464 tonne
2271 Carriage of G.I. pipes below 100 mm dia tonne 0.099 ₹0.00 ₹0.00
approx. wt. 3.72x26.65=99.14kg = 0.099 tonne.
1215 Welding by electric plant cm 2,320 ₹2.50 ₹5,800.00
23.20 m = 2320cm
LABOUR
0102 Blacksmith 1st class day 1.85 ₹897.00 ₹1,659.45
0114 Beldar day 1.25 ₹736.00 ₹920.00
0100 Bandhani day 0.6 ₹816.00 ₹489.60
Applying priming coat
(i) steps 2.4x14 = 33.60sqm.+
(ii) angles-4x12.69x0.25 = 12.69sqm.+
(iii) Bars and other components =
2.00 sqm. (L.S.)
Total = 48.29 sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 48.29 ₹67.40 ₹3,254.75
9999 Sundries L.S. 110.89 ₹2.27 ₹251.72

Rate build-up

TOTAL ₹47,279.34
Add 1 % Water charges on "W-A" ₹440.25
TOTAL ₹47,719.59
Add GST on "X-A" (multiplying factor 0.2127) ₹9,457.67
TOTAL ₹57,177.26
Add 15% CPOH on "Y-A" ₹8,088.38
TOTAL ₹65,265.64
Add Cess @ 1% on "Z-A" ₹620.11
Cost of 5.331 qunital ₹65,885.75
Cost per kg. ₹123.59
Say ₹123.60