Rate Analysis

What is CPOH in Rate Analysis? Full Form, Meaning & Calculation

By Saurabh · Updated 10 July 2026 · 5 min read
TL;DR

CPOH stands for Contractor's Profit & Overheads — a percentage (conventionally 15% in CPWD-style rate analysis) added on top of material, labour, and water charges to cover site establishment, supervision, and the contractor's margin. It is applied before cess and GST.

If you've seen CPOH in a rate analysis sheet and weren't sure what it stood for or why it's there, this guide covers the full form, what it actually pays for, where exactly it sits in the build-up of a unit rate, and a complete worked calculation.

What is the full form of CPOH?

CPOH stands for Contractor's Profit & Overheads. It is a single combined percentage — not two separate line items — added to the cost of material and labour to account for what it costs a contractor to actually run the job site, plus their profit margin on the work.

What does CPOH actually cover?

CPOH is a bundle of three things, rolled into one percentage rather than itemised separately:

CPOH ≈ 15%Site establishmentsite office, storage, temporary works, securitySupervision & administrationsite engineers, supervisory staff, overheadsContractor's profit marginreturn on the work executed
CPOH is not pure profit — it bundles site running costs with the contractor's margin.

Where CPOH sits in the rate build-up

A unit rate is built up in a fixed order — material and labour first, then water charges, then CPOH, then cess, and finally GST on top of everything:

Rate = Material + Labour + Water charges + CPOH + Cess + GST

CPOH is calculated as a percentage of the material + labour + water chargessubtotal — not on the final GST-inclusive figure, and not on cess (cess is added afterwards).

Worked example — CPOH calculation step by step

Take an item where material + labour comes to ₹6,000, with 1% water charges and 1% cess:

CPOH here is 15% of ₹6,060 (material + labour + water charges) = ₹909, taking the running total to ₹6,969 — before cess and GST are layered on top.

Is CPOH always 15%?

15% is the conventional CPWD figure and the one most commonly used across DSR and NSR rate analysis. It isn't a fixed statutory number, though — some departments, contract conditions, or specific works can specify a different percentage. Always check the applicable schedule or contract clause rather than assuming 15% by default.

Is CPOH the same as contractor's profit?

No — profit is only part of CPOH. The rest covers the real, unavoidable cost of running a site: establishment, temporary facilities, and supervisory staff. Treating CPOH as pure profit understates what a contractor actually spends to execute the work.

See it applied live: build a rate on the NSR Items or DSR Workbook pages and Mulyankan shows the CPOH component separately in the breakdown — free, with a PDF export.

For the complete build-up of a unit rate — not just the CPOH step — see the full rate analysis guide.

Frequently asked questions

What is the full form of CPOH?
CPOH stands for Contractor's Profit & Overheads — a single percentage covering site establishment, supervision, and the contractor's profit margin.
What percentage is CPOH in CPWD rate analysis?
The conventional figure is 15%, applied to the material + labour + water-charges subtotal. Some departments or contracts may specify a different percentage.
Is CPOH applied before or after GST?
Before. The order is material + labour, then water charges, then CPOH, then cess, and GST is applied last on the fully built-up rate.
Is GST charged on the CPOH amount too?
Yes — GST is applied on the final rate after CPOH and cess have already been added, so it effectively applies to the CPOH portion as well.
Does CPOH percentage ever change?
15% is the CPWD convention, but specific departments, states, or contract conditions can specify a different CPOH percentage — always confirm against the applicable schedule.
Saurabh
Builds and maintains Mulyankan · Delhi, India · About & methodology

More guides