DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.5.1.1 rate analysis

Providing and fixing panelled or panelled and glazed shutters for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, excluding panelling which will be paid for separately, all complete as per direction of Engineer-in-charge. (Note:- Butt hinges and necessary screws shall be paid separately) Second class teak wood 35 mm thick shutters

Published rate₹4,111.95per sqm
Rate analysis

Providing and fixing panelled or panelled and glazed shutters for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, excluding panelling which will be paid for separately, all complete as per direction of Engineer-in-charge. (Note:- Butt hinges and necessary screws shall be paid separately) Second class teak wood

DSR rate₹4,111.95per sqm

35 mm thick shutters

Item code
9.5.1.1
Sub-head
SH 9 · WOOD & PVC WORK
Unit
sqm
Source row
243

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for shutters of a Door
(1/3rd glazed and 2/3rd panelled) 200x
108cm = 2.16 sqm)
MATERIAL
Teak wood
Styles 4x200x10.0x3.5cm = 0.028cum+ Rails
Top rails 1x110.5x10.0x3.5cm = 0.004cum.+
Bottom rails 1x110.5x20x3.5cm = 0.008cum+
Lock rails 1x110.5x15x3.5cm = 0.006cum+
Beading 2x186.1x1.9x1.2cm = 0.001cum.
Total = 0.047 cum+
Add for wastage @ 10% = 0.005cum
Grand Total = 0.051 cum = 51 cudm
1190 Second class teak wood in planks 10 cudm 5.1 ₹791.00 ₹4,034.10
2204 Carriage of Timber cum 0.051 ₹0.00 ₹0.00
LABOUR
0156 Carpenter (average) day 1.83 ₹857.00 ₹1,568.31
0114 Beldar day 0.76 ₹736.00 ₹559.36
9999 Sundries L.S. 35.88 ₹2.27 ₹81.45

Rate build-up

TOTAL ₹6,243.22
Add 1 % Water charges on "W" ₹62.43
TOTAL ₹6,305.65
Add GST on "X" (multiplying factor 0.2127) ₹1,341.21
TOTAL ₹7,646.86
Add 15% CPOH on "Y" ₹1,147.03
TOTAL ₹8,793.89
Add Cess @ 1% on "Z" ₹87.94
Cost of 2.16 sqm. ₹8,881.83
Cost of 1 sqm. ₹4,111.96
Say ₹4,111.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook