DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.43 rate analysis

Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI marked IS : 14842, including top cover of 6 mm coir veneer board, nickle plated M.S. Pipe 20 mm dia. (heavy type) curtain rod with nickel plated brackets, including fixing with 25x3 mm M.S. Flat 10 cm long fixed to pelmet with hollock wood cleats of size 100 mm x 40 mm x 40 mm on both inner side of pelmet and rawl plugs 75 mm long etc. all complete.

Published rate₹725.85per metre
Rate analysis

Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI marked IS : 14842, including top cover of 6 mm coir veneer board, nickle plated M.S. Pipe 20 mm dia. (heavy type) curtain rod with nickel plated brackets, including fixing with 25x3 mm M.S. Flat 10 cm long fixed to pelmet with hollock wood cleats of size 100 mm x 40 mm x 40 mm on both inner side of pelmet and rawl plugs 75 mm long etc. all complete.

DSR rate₹725.85per metre
Item code
9.43
Sub-head
SH 9 · WOOD & PVC WORK
Unit
metre
Source row
2516

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a pelmet 2m long
MATERIAL
(i) 18mm thick Coir veneered board
Front-1x1.7x0.15= 0.255sqm.+
Sides-2x0.15x0.15= 0.045sqm.
Total = 0.300sqm.+
Add wastage @5% = 0.015sqm.
Total = 0.315sqm. Say 0.32 sqm.
7556 Coir veneered board 18mm thick sqm 0.32 ₹980.00 ₹313.60
6mm thick commercial ply wood
Top-1x1.7x0.15= 0.255sqm.+
Add wastage @ 5% = 0.013 sqm.
Total = 0.268 sqm. Say 0.27 sqm.
7553 Coir veneered board 6mm thick sqm 0.27 ₹368.00 ₹99.36
7034 Nickle plated M.S. pipe 20 mm dia. metre 1.65 ₹78.00 ₹128.70
7035 Nickle plated M.S. Brackets for curtain rod 20 mm each 2 ₹7.00 ₹14.00
9977 Carriage of material L.S. 0.52 ₹2.27 ₹1.18
9999 M.S. flat 25x3mm and 10cm long over brackets L.S. 8.06 ₹2.27 ₹18.30
2505 Hollock wood in planks 10 cudm 0.032 ₹409.00 ₹13.09
7048 Rawl plug 50 mm (designation 10 no.) each 2 ₹24.00 ₹48.00
LABOUR
0112 Carpenter 2nd class day 0.18 ₹816.00 ₹146.88
0114 Beldar day 0.18 ₹736.00 ₹132.48
0130 Mistry day 0.11 ₹897.00 ₹98.67
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹1,020.46
Add 1 % Water charges on "W" ₹10.20
TOTAL ₹1,030.66
Add GST on "X" (multiplying factor 0.2127) ₹219.22
TOTAL ₹1,249.88
Add 15% CPOH on "Y" ₹187.48
TOTAL ₹1,437.36
Add Cess @ 1% on "Z" ₹14.37
Cost of 2 m ₹1,451.73
Cost of 1 metre ₹725.87
Say ₹725.85