DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.4.2 rate analysis

Extra for additional labour for circular works, such as in frames of fan light Sal wood

Published rate₹11,652.05per cum
Rate analysis

Extra for additional labour for circular works, such as in frames of fan light

DSR rate₹11,652.05per cum

Sal wood

Item code
9.4.2
Sub-head
SH 9 · WOOD & PVC WORK
Unit
cum
Source row
171

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for Chowkhat of 10 Nos. door
206.75x117.5cm
Extra Materials and labour for wastage @ 10% on quantity of item no 9.1.2
MATERIAL
1199 Sal wood in scantling 10 cudm 3.8 ₹600.00 ₹2,280.00
2204 Carriage of Timber cum 0.038 ₹0.00 ₹0.00
LABOUR
0156 Carpenter (average) day 0.72 ₹857.00 ₹617.04
0114 Beldar day 0.07 ₹736.00 ₹51.52

Rate build-up

TOTAL ₹2,948.56
Add 1 % Water charges on "W" ₹29.49
TOTAL ₹2,978.05
Add GST on "X" (multiplying factor 0.2127) ₹633.43
TOTAL ₹3,611.48
Add 15% CPOH on "Y" ₹541.72
TOTAL ₹4,153.20
Add Cess @ 1% on "Z" ₹41.53
Cost of 360 cudm=0.36 cum ₹4,194.73
Cost per cum. ₹11,652.03
Say ₹11,652.05

Use this rate in the interactive workbook