DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.4.1 rate analysis

Extra for additional labour for circular works, such as in frames of fan light Second class teak wood

Published rate₹14,294.95per cum
Rate analysis

Extra for additional labour for circular works, such as in frames of fan light

DSR rate₹14,294.95per cum

Second class teak wood

Item code
9.4.1
Sub-head
SH 9 · WOOD & PVC WORK
Unit
cum
Source row
171

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for Chowkhat of 10 Nos. door
206.75x117.5cm
Extra Materials and labour for wastage @ 10% on quantity of item no 9.1.1
MATERIAL
1189 Second class teak wood in scantling 10 cudm 3.8 ₹776.00 ₹2,948.80
2204 Carriage of Timber cum 0.038 ₹0.00 ₹0.00
LABOUR
0156 Carpenter (average) day 0.72 ₹857.00 ₹617.04
0114 Beldar day 0.07 ₹736.00 ₹51.52

Rate build-up

TOTAL ₹3,617.36
Add 1 % Water charges on "W" ₹36.17
TOTAL ₹3,653.53
Add GST on "X" (multiplying factor 0.2127) ₹777.11
TOTAL ₹4,430.64
Add 15% CPOH on "Y" ₹664.60
TOTAL ₹5,095.24
Add Cess @ 1% on "Z" ₹50.95
Cost of 360 cudm=0.36 cum ₹5,146.19
Cost per cum. ₹14,294.97
Say ₹14,294.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook