DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.157.2 rate analysis

Providing and fixing Pre-laminated medium density fibre board IS: 14587:1998 marked, with one side decorative lamination other side balancing lamination Grade-I(exterior grade) in shelves with screws and fittings wherever required, edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand (fittings to be paid separately). Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick confirming to IS:14587

Published rate₹1,874.70per sqm
Rate analysis

Providing and fixing Pre-laminated medium density fibre board IS: 14587:1998 marked, with one side decorative lamination other side balancing lamination Grade-I(exterior grade) in shelves with screws and fittings wherever required, edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand (fittings to be paid separately).

DSR rate₹1,874.70per sqm

Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick confirming to IS:14587

Item code
9.157.2
Sub-head
SH 9 · WOOD & PVC WORK
Unit
sqm
Source row
10016

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 0.60 sqm.
Detail of cost for 4 Nos. 75x20 cm
shelves = 0.60 sqm
MATERIAL
25 mm Thick MDF Board outside laminated = 0.60 sqm
Add wastage @ 5% = 0.03 sqm
Total= 0.63 sqm
2486 Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick confirming to IS:14587 sqm 0.63 ₹903.00 ₹568.89
PVC edge bending tape 2.00 mm thick 4X 0.75 =3.00 metre
2489 PVC edge bending tape 2.00 mm thick metre 3 ₹22.00 ₹66.00
9999 Sundries (Carriage of MDF board) L.S. 1.82 ₹2.27 ₹4.13
LABOUR
0112 Carpenter 2nd class day 0.11 ₹816.00 ₹89.76
0114 Beldar day 0.06 ₹736.00 ₹44.16
9999 Sundries and screws L.S. 7.8 ₹2.27 ₹17.71

Rate build-up

TOTAL ₹790.65
Add 1 % Water charges on "W" ₹7.91
TOTAL ₹798.56
Add GST on "X" (multiplying factor 0.2127) ₹169.85
TOTAL ₹968.41
Add 15% CPOH on "Y" ₹145.26
TOTAL ₹1,113.67
Add Cess @ 1% on "Z" ₹11.14
Cost of 0.60 sqm. ₹1,124.81
Cost of 1 sqm. ₹1,874.68
Say ₹1,874.70