Rate analysis
Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) : White sand stone - Exposed face machine cut and table rubbed with rough backing.
DSR rate₹8,330.65per sqm
40 mm thick
- Item code
- 8.14.4.4
- Sub-head
- SH 8 · CLADDING WORK
- Unit
- sqm
- Source row
- 593
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 sqm. | |||||
| MATERIAL | |||||
| Finished work = 40 cudm+Add wastage @ 33.3% = 13.3 cudm. Total = 53.3 cudm. | |||||
| 1161 | White sand stone block | 10 cudm | 5.33 | ₹205.00 | ₹1,092.65 |
| 2216 | Carriage of Stone blocks white & red sand stone & kota stone slab | tonne | 0.123 | ₹0.00 | ₹0.00 |
| @ 2.30 kg/cudm. | |||||
| 9999 | Extra for using white cement | L.S. | 26.91 | ₹2.27 | ₹61.09 |
| Dressing charges | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 2.7 | ₹816.00 | ₹2,203.20 |
| 0102 | Blacksmith 1st class | day | 0.064 | ₹897.00 | ₹57.41 |
| 0114 | Beldar | day | 0.448 | ₹736.00 | ₹329.73 |
| 0115 | Coolie | day | 0.224 | ₹736.00 | ₹164.86 |
| 0100 | Bandhani | day | 0.448 | ₹816.00 | ₹365.57 |
| Fixing charges | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 0.448 | ₹816.00 | ₹365.57 |
| 0100 | Bandhani | day | 0.336 | ₹816.00 | ₹274.18 |
| 0114 | Beldar | day | 0.336 | ₹736.00 | ₹247.30 |
| 0115 | Coolie | day | 0.336 | ₹736.00 | ₹247.30 |
| 0101 | Bhisti | day | 0.336 | ₹816.00 | ₹274.18 |
| 1237 | Cutting marble or sand stone slab upto 50 mm thick by mechanical device | metre | 4 | ₹10.00 | ₹40.00 |
| 9999 | Scaffolding | L.S. | 19.76 | ₹2.27 | ₹44.86 |
| Mortar for laying and pointing | |||||
| 3.8 | Rate as per Item Number 3.8 of SH: Mortars | cum | 0.018 | ₹4,881.95 | ₹87.88 |
Rate build-up
| TOTAL | ₹5,855.78 |
| Add 1 % Water charges on "W" | ₹58.56 |
| TOTAL | ₹5,914.34 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,257.98 |
| TOTAL | ₹7,172.32 |
| Add 15% CPOH on "Y" | ₹1,075.85 |
| TOTAL | ₹8,248.17 |
| Add Cess @ 1% on "Z" | ₹82.48 |
| Cost of 1 sqm. | ₹8,330.65 |
| Say | ₹8,330.65 |