DSR 2023 · SH 8 · CLADDING WORK

CPWD DSR item 8.14.4.3 rate analysis

Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) : White sand stone - Exposed face machine cut and table rubbed with rough backing. 50 mm thick

Published rate₹8,721.45per sqm
Rate analysis

Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) : White sand stone - Exposed face machine cut and table rubbed with rough backing.

DSR rate₹8,721.45per sqm

50 mm thick

Item code
8.14.4.3
Sub-head
SH 8 · CLADDING WORK
Unit
sqm
Source row
593

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 sqm.
MATERIAL
Finished work = 50 cudm+Add wastage @ 33.3% = 16.7 cudm. Total = 66.7 cudm.
1161 White sand stone block 10 cudm 6.67 ₹205.00 ₹1,367.35
2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 0.153 ₹0.00 ₹0.00
@ 2.30 kg/cudm.
9999 Extra for using white cement L.S. 26.91 ₹2.27 ₹61.09
Dressing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 2.7 ₹816.00 ₹2,203.20
0102 Blacksmith 1st class day 0.064 ₹897.00 ₹57.41
0114 Beldar day 0.448 ₹736.00 ₹329.73
0115 Coolie day 0.224 ₹736.00 ₹164.86
0100 Bandhani day 0.448 ₹816.00 ₹365.57
Fixing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.448 ₹816.00 ₹365.57
0100 Bandhani day 0.336 ₹816.00 ₹274.18
0114 Beldar day 0.336 ₹736.00 ₹247.30
0115 Coolie day 0.336 ₹736.00 ₹247.30
0101 Bhisti day 0.336 ₹816.00 ₹274.18
1237 Cutting marble or sand stone slab upto 50 mm thick by mechanical device metre 4 ₹10.00 ₹40.00
9999 Scaffolding L.S. 19.76 ₹2.27 ₹44.86
Mortar for laying and pointing
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.018 ₹4,881.95 ₹87.88

Rate build-up

TOTAL ₹6,130.48
Add 1 % Water charges on "W" ₹61.30
TOTAL ₹6,191.78
Add GST on "X" (multiplying factor 0.2127) ₹1,316.99
TOTAL ₹7,508.77
Add 15% CPOH on "Y" ₹1,126.32
TOTAL ₹8,635.09
Add Cess @ 1% on "Z" ₹86.35
Cost of 1 sqm. ₹8,721.44
Say ₹8,721.45

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook