DSR 2023 · SH 8 · CLADDING WORK

CPWD DSR item 8.1.1.1 rate analysis

Marble work gang saw cut (polished and machine cut) of thickness 18 mm for wall lining (veneer work), backing filled with a grout of average 12 mm thick in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match the marble shade (To be secured to the backing by means of cramps, which shall be paid for separately). Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble. Area of slab upto 0.50 sqm

Published rate₹5,742.55DSR 2023
Rate analysis

Marble work gang saw cut (polished and machine cut) of thickness 18 mm for wall lining (veneer work), backing filled with a grout of average 12 mm thick in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match the marble shade (To be secured to the backing by means of cramps, which shall be paid for separately). Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.

DSR rate₹5,742.55as per item analysis

Area of slab upto 0.50 sqm

Item code
8.1.1.1
Sub-head
SH 8 · CLADDING WORK
Unit
See analysis
Source row
4

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 5 sqm.
MATERIAL
Finished work = 5sqm. Add for wastage @ 20% = 1 sqm. Total = 6 sqm.
7452 Raj nagar plain white marble (table rubbed and polished) 18 mm thick (slab area upto 0.50 sqm) sqm 6 ₹570.00 ₹3,420.00
2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 0.3 ₹0.00 ₹0.00
Cement mortar 1:3 (1 cement : 3 coarse sand)
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.08 ₹4,881.95 ₹390.56
White cement mortar 1:2 (1 white cement : 2 marble dust)
3.15 Rate as per Item Number 3.15 of SH: Mortars cum 0.012 ₹8,961.90 ₹107.54
LABOUR
For fixing
0126 Mason (for ornamental stone work) 1st class day 3.35 ₹897.00 ₹3,004.95
0100 Bandhani day 3.35 ₹816.00 ₹2,733.60
0114 Beldar day 3.35 ₹736.00 ₹2,465.60
0115 Coolie day 3.35 ₹736.00 ₹2,465.60
0101 Bhisti day 3.35 ₹816.00 ₹2,733.60
0128 Mate day 1.65 ₹816.00 ₹1,346.40
0102 Blacksmith 1st class day 1.35 ₹897.00 ₹1,210.95
9999 Scaffolding L.S. 133.9 ₹2.27 ₹303.95

Rate build-up

TOTAL ₹20,182.75
Add 1 % Water charges on "W" ₹201.83
TOTAL ₹20,384.58
Add GST on "X" (multiplying factor 0.2127) ₹4,335.80
TOTAL ₹24,720.38
Add 15% CPOH on "Y" ₹3,708.06
TOTAL ₹28,428.44
Add Cess @ 1% on "Z" ₹284.28
Cost for 5 sqm. ₹28,712.72
Cost for one sqm. ₹5,742.54
Say ₹5,742.55