DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.35 rate analysis

Extra for laying stone work in or under foul condition.

Published rate₹467.55DSR 2023
Rate analysis

Extra for laying stone work in or under foul condition.

DSR rate₹467.55as per item analysis
Item code
7.35
Sub-head
SH 7 · STONE WORK
Unit
See analysis
Source row
1571

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
Extra labour due to slow progress-
0123 Mason 1st class day 0.02 ₹897.00 ₹17.94
0124 Mason 2nd class day 0.02 ₹816.00 ₹16.32
0114 Beldar day 0.25 ₹736.00 ₹184.00
0115 Coolie day 0.15 ₹736.00 ₹110.40

Rate build-up

TOTAL ₹328.66
Add 1 % Water charges on "W" ₹3.29
TOTAL ₹331.95
Add GST on "X" (multiplying factor 0.2127) ₹70.61
TOTAL ₹402.56
Add 15% CPOH on "Y" ₹60.38
TOTAL ₹462.94
Add Cess @ 1% on "Z" ₹4.63
Cost for 1 cum. ₹467.57
Say ₹467.55

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook