Rate analysis
Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub-soil water level up to the centre of gravity of stone work under sub - water with the quantity of stone work in cum executed under the sub-soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, 0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored.
DSR rate₹1,098.80as per item analysis
- Item code
- 7.34
- Sub-head
- SH 7 · STONE WORK
- Unit
- See analysis
- Source row
- 1550
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 4.2 cum per 1 m depth (14 cum per 0.3m depth) | |||||
| Quantity of concrete = 14 cum. | |||||
| pumping hours = 3 hrs. on 0.375day. | |||||
| 0011 | Hire charges of Pumpset of capacity 4000 litres/hour. | day | 0.375 | ₹800.00 | ₹300.00 |
| for cleaning slush | |||||
| 0114 | Beldar | day | 4 | ₹736.00 | ₹2,944.00 |
Rate build-up
| TOTAL | ₹3,244.00 |
| Add 1 % Water charges on "W" | ₹32.44 |
| TOTAL | ₹3,276.44 |
| Add GST on "X" (multiplying factor 0.2127) | ₹696.90 |
| TOTAL | ₹3,973.34 |
| Add 15% CPOH on "Y" | ₹596.00 |
| TOTAL | ₹4,569.34 |
| Add Cess @ 1% on "Z" | ₹45.69 |
| Cost of 4.2cum per 1 metre depth | ₹4,615.03 |
| Cost of cum per metre depth | ₹1,098.82 |
| Say | ₹1,098.80 |