DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.22 rate analysis

Extra for stone work ashlar sunk or moulded in cornices.

Published rate₹303.50DSR 2023
Rate analysis

Extra for stone work ashlar sunk or moulded in cornices.

DSR rate₹303.50as per item analysis
Item code
7.22
Sub-head
SH 7 · STONE WORK
Unit
See analysis
Source row
1190

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a cornice 30cm long, 60cm deep and 15cm projection
Extra labour :
0125 Mason (for plain stone work) 2nd class) day 0.5 ₹816.00 ₹408.00
0114 Beldar day 0.75 ₹736.00 ₹552.00

Rate build-up

TOTAL ₹960.00
Add 1 % Water charges on "W" ₹9.60
TOTAL ₹969.60
Add GST on "X" (multiplying factor 0.2127) ₹206.23
TOTAL ₹1,175.83
Add 15% CPOH on "Y" ₹176.37
TOTAL ₹1,352.20
Add Cess @ 1% on "Z" ₹13.52
Cost of 30cm long 60cm deep and 15cm girth ₹1,365.72
Cost of per metre per cm girth (60cm deep) ₹303.49
Say ₹303.50