DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.21.2 rate analysis

Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in : Circular or polygonal pillars

Published rate₹10,706.00per cum
Rate analysis

Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in :

DSR rate₹10,706.00per cum

Circular or polygonal pillars

Item code
7.21.2
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
1157

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cudm or 0.01 cum
9999 LABOUR L.S. 33.15 ₹2.27 ₹75.25

Rate build-up

TOTAL ₹75.25
Add 1 % Water charges on "W" ₹0.75
TOTAL ₹76.00
Add GST on "X" (multiplying factor 0.2127) ₹16.17
TOTAL ₹92.17
Add 15% CPOH on "Y" ₹13.83
TOTAL ₹106.00
Add Cess @ 1% on "Z" ₹1.06
Cost of 10 cudm. ₹107.06
Cost of 1 cum. ₹10,706.00
Say ₹10,706.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook