DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.15.2.1 rate analysis

Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1 white cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade. Both faced punched Red sand stone

Published rate₹84,560.00per cum
Rate analysis

Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1 white cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade. Both faced punched

DSR rate₹84,560.00per cum

Red sand stone

Item code
7.15.2.1
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
805

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cudm or 0.01 cum
MATERIAL
1160 Red sand stone block 10 cudm 1.333 ₹130.00 ₹173.29
Finished work = 10 cudm. Add wastage @ 33.3% = 3.33 cudm. Total = 13.33 cudm
2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 0.031 ₹0.00 ₹0.00
@ 2.30kg/cudm = 13.33x2.30 = 30.659 tonne = 0.03065 kg say 0.031 t.
Extra labour for lifting of materials upto floor V level 0.01x1.50 = 0.015
0115 Coolie day 0.015 ₹736.00 ₹11.04
Dressing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.118 ₹816.00 ₹96.29
0102 Blacksmith 1st class day 0.012 ₹897.00 ₹10.76
0114 Beldar day 0.088 ₹736.00 ₹64.77
0115 Coolie day 0.044 ₹736.00 ₹32.38
0100 Bandhani day 0.088 ₹816.00 ₹71.81
Fixing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.044 ₹816.00 ₹35.90
0102 Blacksmith 1st class day 0.006 ₹897.00 ₹5.38
0114 Beldar day 0.022 ₹736.00 ₹16.19
0115 Coolie day 0.022 ₹736.00 ₹16.19
0100 Bandhani day 0.022 ₹816.00 ₹17.95
0101 Bhisti day 0.022 ₹816.00 ₹17.95
9999 Scafolding L.S. 2.73 ₹2.27 ₹6.20
9999 Mortar for laying and pointing L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹594.40
Add 1 % Water charges on "W" ₹5.94
TOTAL ₹600.34
Add GST on "X" (multiplying factor 0.2127) ₹127.69
TOTAL ₹728.03
Add 15% CPOH on "Y" ₹109.20
TOTAL ₹837.23
Add Cess @ 1% on "Z" ₹8.37
Cost of 10 cudm. ₹845.60
Cost of 1 cum. ₹84,560.00
Say ₹84,560.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook