Rate analysis
Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor V level, for each four floors or part thereof by mechanical means.
DSR rate₹169.45as per item analysis
- Item code
- 6.5
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 220
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 5.3 cum per four floors . | |||||
| 0037 | Mobile crane | day | 0.125 | ₹5,050.00 | ₹631.25 |
Rate build-up
| TOTAL | ₹631.25 |
| Add 1 % Water charges on "W" | ₹6.31 |
| TOTAL | ₹637.56 |
| Add GST on "X" (multiplying factor 0.2127) | ₹135.61 |
| TOTAL | ₹773.17 |
| Add 15% CPOH on "Y" | ₹115.98 |
| TOTAL | ₹889.15 |
| Add Cess @ 1% on "Z" | ₹8.89 |
| Cost of 5.3 Cum. | ₹898.04 |
| Cost for 1 cum | ₹169.44 |
| Say | ₹169.45 |