DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.5 rate analysis

Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor V level, for each four floors or part thereof by mechanical means.

Published rate₹169.45DSR 2023
Rate analysis

Extra for brick work / AAC block masonry / Tile brick masonry in superstructure above floor V level, for each four floors or part thereof by mechanical means.

DSR rate₹169.45as per item analysis
Item code
6.5
Sub-head
SH 6 · MASONRY WORK
Unit
See analysis
Source row
220

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 5.3 cum per four floors .
0037 Mobile crane day 0.125 ₹5,050.00 ₹631.25

Rate build-up

TOTAL ₹631.25
Add 1 % Water charges on "W" ₹6.31
TOTAL ₹637.56
Add GST on "X" (multiplying factor 0.2127) ₹135.61
TOTAL ₹773.17
Add 15% CPOH on "Y" ₹115.98
TOTAL ₹889.15
Add Cess @ 1% on "Z" ₹8.89
Cost of 5.3 Cum. ₹898.04
Cost for 1 cum ₹169.44
Say ₹169.45

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook