Rate analysis
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in :
DSR rate₹9,105.95per Cum
Cement mortar 1:6 (1 cement : 6 coarse sand)
- Item code
- 6.4.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- Cum
- Source row
- 163
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.494 | ₹4,724.00 | ₹2,333.66 |
| Cement mortar 1 : 6 | |||||
| 3.11 | Rate as per Item Number 3.11 of SH: Mortars | cum | 0.25 | ₹3,541.40 | ₹885.35 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.494 | ₹0.00 | ₹0.00 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.47 | ₹897.00 | ₹421.59 |
| 0124 | Mason 2nd class | day | 0.47 | ₹816.00 | ₹383.52 |
| 0115 | Coolie | day | 1.8 | ₹736.00 | ₹1,324.80 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
| 9999 | Scaffolding | L.S. | 22.36 | ₹2.27 | ₹50.76 |
| Extra labour element required for lifting of materials (above floor two level upto floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
Rate build-up
| TOTAL | ₹6,400.76 |
| Add 1 % Water charges on "W" | ₹64.01 |
| TOTAL | ₹6,464.77 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,375.06 |
| TOTAL | ₹7,839.83 |
| Add 15% CPOH on "Y" | ₹1,175.97 |
| TOTAL | ₹9,015.80 |
| Add Cess @ 1% on "Z" | ₹90.16 |
| Cost of 1 Cum. | ₹9,105.96 |
| Say | ₹9,105.95 |