DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.4.2 rate analysis

Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : Cement mortar 1:6 (1 cement : 6 coarse sand)

Published rate₹9,105.95per Cum
Rate analysis

Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in :

DSR rate₹9,105.95per Cum

Cement mortar 1:6 (1 cement : 6 coarse sand)

Item code
6.4.2
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
163

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
MATERIAL
2602 Common burnt clay F.P.S. (non modular) bricks class designation 7.5 1000 Nos 0.494 ₹4,724.00 ₹2,333.66
Cement mortar 1 : 6
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.25 ₹3,541.40 ₹885.35
2201 Carriage of Bricks 1000 Nos 0.494 ₹0.00 ₹0.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.47 ₹897.00 ₹421.59
0124 Mason 2nd class day 0.47 ₹816.00 ₹383.52
0115 Coolie day 1.8 ₹736.00 ₹1,324.80
0101 Bhisti day 0.2 ₹816.00 ₹163.20
9999 Scaffolding L.S. 22.36 ₹2.27 ₹50.76
Extra labour element required for lifting of materials (above floor two level upto floor five level)
0115 Coolie day 1.13 ₹736.00 ₹831.68

Rate build-up

TOTAL ₹6,400.76
Add 1 % Water charges on "W" ₹64.01
TOTAL ₹6,464.77
Add GST on "X" (multiplying factor 0.2127) ₹1,375.06
TOTAL ₹7,839.83
Add 15% CPOH on "Y" ₹1,175.97
TOTAL ₹9,015.80
Add Cess @ 1% on "Z" ₹90.16
Cost of 1 Cum. ₹9,105.96
Say ₹9,105.95