Rate analysis
Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry with 150mm to 300 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level with RCC band at sill level and lintel level with approved block laying polymer modified adhesive mortar all complete as per direction of Engineer-in-Charge. (The payment of RCC band and reinforcement shall be made for seperately).
DSR rate₹8,333.65per cum
- Item code
- 6.47
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- cum
- Source row
- 1550
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 8655 | Autoclaved aerated concrete (AAC) blocks (grade 1 of density 551 to 650 kg/cum) | cum | 1 | ₹2,915.00 | ₹2,915.00 |
| 0357 | Polymer modified adhesive mortar | Kg | 30 | ₹16.00 | ₹480.00 |
| 2208 | Carriage of AAC blocks | Cum | 1 | ₹0.00 | ₹0.00 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| LABOUR | |||||
| 0123 | Mason (brick layer) 1 st class | day | 0.36 | ₹897.00 | ₹322.92 |
| 0124 | Mason 2nd class | day | 0.36 | ₹816.00 | ₹293.76 |
| 0115 | Coolie | day | 1.37 | ₹736.00 | ₹1,008.32 |
| Extra labour element required for lifting of materials (above floor two level upto floor five level) (0.75x1.50 = 1.13) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
Rate build-up
| TOTAL | ₹5,857.88 |
| Add 1 % Water charges on "W" | ₹58.58 |
| TOTAL | ₹5,916.46 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,258.43 |
| TOTAL | ₹7,174.89 |
| Add 15% CPOH on "Y" | ₹1,076.23 |
| TOTAL | ₹8,251.12 |
| Add Cess @ 1% on "Z" | ₹82.51 |
| Cost of 1 cum | ₹8,333.63 |
| Say | ₹8,333.65 |