Rate analysis
Half brick masonry with non modular fly ash bricks of class designation 10, conformingio IS :12894, in super structure above plinth and upto floor V level.
DSR rate₹1,105.80as per item analysis
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
- Item code
- 6.45.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 1493
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 sqm. | |||||
| MATERIAL | |||||
| 7737 | Fly ash bricks conforming to I.S. 12894 | 1000 Nos | 0.565 | ₹4,500.00 | ₹2,542.50 |
| Cement mortar 1 : 4 (1 cement : 4 coarse sand) | |||||
| 3.9 | Rate as per Item Number 3.9 of SH: Mortars | cum | 0.28 | ₹4,211.70 | ₹1,179.28 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.565 | ₹0.00 | ₹0.00 |
| 9999 | Sundries & Scaffolding | L.S. | 13.52 | ₹2.27 | ₹30.69 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.6 | ₹897.00 | ₹538.20 |
| 0124 | Mason 2nd class | day | 0.6 | ₹816.00 | ₹489.60 |
| 0115 | Coolie | day | 2 | ₹736.00 | ₹1,472.00 |
| 0101 | Bhisti | day | 0.7 | ₹816.00 | ₹571.20 |
| Extra labour for lifting of material (above floor two level up to floor five level) | |||||
| 0115 | Coolie | day | 1.29 | ₹736.00 | ₹949.44 |
Rate build-up
| TOTAL | ₹7,772.91 |
| Add 1 % Water charges on "W" | ₹77.73 |
| TOTAL | ₹7,850.64 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,669.83 |
| TOTAL | ₹9,520.47 |
| Add 15% CPOH on "Y" | ₹1,428.07 |
| TOTAL | ₹10,948.54 |
| Add Cess @ 1% on "Z" | ₹109.49 |
| Cost for 10 sqm. | ₹11,058.03 |
| Cost for 1 sqm. | ₹1,105.80 |
| Say | ₹1,105.80 |