DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.34.1 rate analysis

Brick work with non modular fly ash bricks conforming to IS:12894, class designation 10 average compressive strength in super structure above plinth level up to floor V level in : Cement mortar 1:4 (1 cement : 4 coarse sand)

Published rate₹8,962.35per cum
Rate analysis

Brick work with non modular fly ash bricks conforming to IS:12894, class designation 10 average compressive strength in super structure above plinth level up to floor V level in :

DSR rate₹8,962.35per cum

Cement mortar 1:4 (1 cement : 4 coarse sand)

Item code
6.34.1
Sub-head
SH 6 · MASONRY WORK
Unit
cum
Source row
1230

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7737 Fly ash bricks conforming to I.S. 12894 1000 Nos 0.487 ₹4,500.00 ₹2,191.50
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.22 ₹4,211.70 ₹926.57
2201 Carriage of Bricks 1000 Nos 0.487 ₹0.00 ₹0.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.47 ₹897.00 ₹421.59
0124 Mason 2nd class day 0.47 ₹816.00 ₹383.52
0115 Coolie day 1.8 ₹736.00 ₹1,324.80
0101 Bhisti day 0.2 ₹816.00 ₹163.20
9999 Scaffolding L.S. 22.36 ₹2.27 ₹50.76
Extra labour element required for lifting of materials above floor two level upto floor V level (0.75 x 1.5 = 1.13)
0115 Coolie day 1.13 ₹736.00 ₹831.68

Rate build-up

TOTAL ₹6,299.82
Add 1 % Water charges on "W" ₹63.00
TOTAL ₹6,362.82
Add GST on "X" (multiplying factor 0.2127) ₹1,353.37
TOTAL ₹7,716.19
Add 15% CPOH on "Y" ₹1,157.43
TOTAL ₹8,873.62
Add Cess @ 1% on "Z" ₹88.74
Cost per cum. ₹8,962.36
Say ₹8,962.35

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook