Rate analysis
Brick work with clay flyash F.P.S. (non modular) brick of class designation 7.5 in superstructure above plinth level up to floor five level in :
DSR rate₹9,095.05per cum
Cement mortar 1:6 (1 cement : 6 coarse sand)
- Item code
- 6.32.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- cum
- Source row
- 1172
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 7008 | F.P.S.(non modular) clay fly ash bricks class designation 7.5 | 1000 Nos | 0.494 | ₹4,770.00 | ₹2,356.38 |
| Cement mortar 1 : 6 (1 cement : 6 coarse sand) | |||||
| 3.11 | Rate as per Item Number 3.11 of | — | — | — | — |
| — | SH: Mortars | cum | 0.25 | ₹3,541.40 | ₹885.35 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.494 | ₹0.00 | ₹0.00 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.47 | ₹897.00 | ₹421.59 |
| 0124 | Mason 2nd class | day | 0.47 | ₹816.00 | ₹383.52 |
| 0115 | Coolie | day | 1.8 | ₹736.00 | ₹1,324.80 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
| 9999 | Scaffolding | L.S. | 8.97 | ₹2.27 | ₹20.36 |
| Extra labour element required for lifting of materials above floor two level upto floor V level (0.75 x 1.5 = 1.13) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
Rate build-up
| TOTAL | ₹6,393.08 |
| Add 1 % Water charges on "W" | ₹63.93 |
| TOTAL | ₹6,457.01 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,373.41 |
| TOTAL | ₹7,830.42 |
| Add 15% CPOH on "Y" | ₹1,174.56 |
| TOTAL | ₹9,004.98 |
| Add Cess @ 1% on "Z" | ₹90.05 |
| Cost per cum. | ₹9,095.03 |
| Say | ₹9,095.05 |