Rate analysis
Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) :
DSR rate₹8,942.35per Cum
With Modular bricks
- Item code
- 6.3.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- Cum
- Source row
- 106
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| MATERIAL | |||||
| 7902 | Machine moulded common burnt clay modular perforated bricks of class designation 12.5 | 1000 Nos | 0.487 | ₹5,500.00 | ₹2,678.50 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.487 | ₹0.00 | ₹0.00 |
| Cement mortar 1 : 6 (1 cement : 6 coarse sand) | |||||
| 3.11 | Rate as per item No 3.11 of SH: Mortar | cum | 0.22 | ₹3,541.40 | ₹779.11 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.44 | ₹897.00 | ₹394.68 |
| 0124 | Mason 2nd class | day | 0.44 | ₹816.00 | ₹359.04 |
| 0115 | Coolie | day | 1.43 | ₹736.00 | ₹1,052.48 |
| 0101 | Bhisti | day | 0.18 | ₹816.00 | ₹146.88 |
| 9999 | Scaffolding | L.S. | 16.38 | ₹2.27 | ₹37.18 |
| Extra labour element required for lifting of materials (above floor two level upto floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
Rate build-up
| TOTAL | ₹6,285.75 |
| Add 1 % Water charges on "W" | ₹62.86 |
| TOTAL | ₹6,348.61 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,350.35 |
| TOTAL | ₹7,698.96 |
| Add 15% CPOH on "Y" | ₹1,154.84 |
| TOTAL | ₹8,853.80 |
| Add Cess @ 1% on "Z" | ₹88.54 |
| Cost of 1 Cum. | ₹8,942.34 |
| Say | ₹8,942.35 |