DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.3.2 rate analysis

Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) : With Modular bricks

Published rate₹8,942.35per Cum
Rate analysis

Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) :

DSR rate₹8,942.35per Cum

With Modular bricks

Item code
6.3.2
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
106

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
MATERIAL
7902 Machine moulded common burnt clay modular perforated bricks of class designation 12.5 1000 Nos 0.487 ₹5,500.00 ₹2,678.50
2201 Carriage of Bricks 1000 Nos 0.487 ₹0.00 ₹0.00
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per item No 3.11 of SH: Mortar cum 0.22 ₹3,541.40 ₹779.11
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.44 ₹897.00 ₹394.68
0124 Mason 2nd class day 0.44 ₹816.00 ₹359.04
0115 Coolie day 1.43 ₹736.00 ₹1,052.48
0101 Bhisti day 0.18 ₹816.00 ₹146.88
9999 Scaffolding L.S. 16.38 ₹2.27 ₹37.18
Extra labour element required for lifting of materials (above floor two level upto floor five level)
0115 Coolie day 1.13 ₹736.00 ₹831.68

Rate build-up

TOTAL ₹6,285.75
Add 1 % Water charges on "W" ₹62.86
TOTAL ₹6,348.61
Add GST on "X" (multiplying factor 0.2127) ₹1,350.35
TOTAL ₹7,698.96
Add 15% CPOH on "Y" ₹1,154.84
TOTAL ₹8,853.80
Add Cess @ 1% on "Z" ₹88.54
Cost of 1 Cum. ₹8,942.34
Say ₹8,942.35

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook