DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.3.1 rate analysis

Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) : With F.P.S.(non modular) bricks

Published rate₹9,299.90per Cum
Rate analysis

Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) :

DSR rate₹9,299.90per Cum

With F.P.S.(non modular) bricks

Item code
6.3.1
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
106

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
MATERIAL
7901 Machine moulded perforated common burnt clay FPS (non modular) bricks of class designation 12.5 1000 Nos 0.494 ₹5,000.00 ₹2,470.00
2201 Carriage of Bricks 1000 Nos 0.494 ₹0.00 ₹0.00
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per item No 3.11 of SH: Mortar cum 0.25 ₹3,541.40 ₹885.35
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.47 ₹897.00 ₹421.59
0124 Mason 2nd class day 0.47 ₹816.00 ₹383.52
0115 Coolie day 1.8 ₹736.00 ₹1,324.80
0101 Bhisti day 0.2 ₹816.00 ₹163.20
9999 Scaffolding L.S. 22.36 ₹2.27 ₹50.76
Extra labour element required for lifting of materials (above floor two level upto floor five level)
0115 Coolie day 1.13 ₹736.00 ₹831.68

Rate build-up

TOTAL ₹6,537.10
Add 1 % Water charges on "W" ₹65.37
TOTAL ₹6,602.47
Add GST on "X" (multiplying factor 0.2127) ₹1,404.35
TOTAL ₹8,006.82
Add 15% CPOH on "Y" ₹1,201.02
TOTAL ₹9,207.84
Add Cess @ 1% on "Z" ₹92.08
Cost of 1 Cum. ₹9,299.92
Say ₹9,299.90

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook