Rate analysis
Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in gauged arch work in superstructure above plinth and upto floor five level in cement mortar 1:4 (1 cement : 4 coarse sand) including centering and shuttering complete.
DSR rate₹23,019.75as per item analysis
- Item code
- 6.21
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 729
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 1984 | Common burnt clay F.P.S. (non modular) bricks tile class designation 10 | 1000 Nos | 0.791 | ₹4,750.00 | ₹3,757.25 |
| 2207 | Carriage of Brick tiles | 1000 Nos | 0.791 | ₹0.00 | ₹0.00 |
| Cement mortar 1 : 4 | |||||
| 3.9 | Rate as per Item Number 3.9 of SH: Mortars | cum | 0.35 | ₹4,211.70 | ₹1,474.10 |
| 9999 | Sundries and shuttering | L.S. | 5.46 | ₹2.27 | ₹12.39 |
| Centering and shuttering, area same as in item no. 6.9 | |||||
| 5.9.9 | Rate as per item no 5.9.9 of SH : Reinforced cement concrete work | sqm | 2.25 | ₹2,154.35 | ₹4,847.29 |
| 9999 | Scaffolding | L.S. | 18.85 | ₹2.27 | ₹42.79 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 1.5 | ₹897.00 | ₹1,345.50 |
| 0124 | Mason 2nd class | day | 1.5 | ₹816.00 | ₹1,224.00 |
| 0115 | Coolie | day | 5.33 | ₹736.00 | ₹3,922.88 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
| Extra labour for lifting of material (above floor two level up to floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
Rate build-up
| TOTAL | ₹17,621.08 |
| Add 1 % Water charges on "W-A" | ₹127.74 |
| TOTAL | ₹17,748.82 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹2,744.16 |
| TOTAL | ₹20,492.98 |
| Add 15% CPOH on "Y-A" | ₹2,346.85 |
| TOTAL | ₹22,839.83 |
| Add Cess @ 1% on "Z-A" | ₹179.93 |
| Cost for 1 cum. | ₹23,019.76 |
| Say | ₹23,019.75 |