Rate analysis
Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in superstructure above plinth level up to floor V level in cement mortar 1:6 (1 cement : 6 coarse sand).
DSR rate₹12,883.05per Cum
- Item code
- 6.18
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- Cum
- Source row
- 671
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 1984 | Common burnt clay F.P.S. (non modular) bricks tile class designation 10 | 1000 Nos | 0.777 | ₹4,750.00 | ₹3,690.75 |
| 2207 | Carriage of Brick tiles | 1000 Nos | 0.777 | ₹0.00 | ₹0.00 |
| Cement mortar 1 : 6 | |||||
| 3.11 | Rate as per Item Number 3.11 of SH: Mortars | cum | 0.4 | ₹3,541.40 | ₹1,416.56 |
| 9999 | Sundries | L.S. | 4.55 | ₹2.27 | ₹10.33 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.9 | ₹897.00 | ₹807.30 |
| 0124 | Mason 2nd class | day | 0.9 | ₹816.00 | ₹734.40 |
| 0115 | Coolie | day | 1.8 | ₹736.00 | ₹1,324.80 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
| Extra labour for lifting of materials | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
| 9999 | Scaffolding | L.S. | 33.8 | ₹2.27 | ₹76.73 |
Rate build-up
| TOTAL | ₹9,055.75 |
| Add 1 % Water charges on "W" | ₹90.56 |
| TOTAL | ₹9,146.31 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,945.42 |
| TOTAL | ₹11,091.73 |
| Add 15% CPOH on "Y" | ₹1,663.76 |
| TOTAL | ₹12,755.49 |
| Add Cess @ 1% on "Z" | ₹127.55 |
| Cost of 1 Cum. | ₹12,883.04 |