DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.16.2 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls Above 20 cm wide

Published rate₹879.05per sqm
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls

DSR rate₹879.05per sqm

Above 20 cm wide

Item code
5.9.16.2
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
sqm
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10Nos of size 4mx4m slab 25cm thick
16 metre edge length
Shuttering surface area = 10x16 x 0.25 = 40 sqm
MATERIAL
1198 Second class kail wood in planks 10 cudm 20 ₹260.00 ₹5,200.00
(i) Planks 38mm thick
10x4x4x0.25x0.038 = 1.52
Wastage @ 5% = 0.08
Total = 1.60 cum. = 1600 cudm
Qty taken for cost of using once = 1600/8 = 200 cudm
1197 Second class kail wood in scantling 10 cudm 21.88 ₹260.00 ₹5,688.80
(ii) Battens
10x6x2x0.6x0.075x0.100=0.54
10x5x2x1.5x0.075x0.100=1.13
Total = 1.67
Wastage @ 5% = 0.08
Total= 1.75 cum. = 1750 cudm
Qty taken for cost of using once = 1750/8 = 218.8 cudm
2204 Carriage of Timber cum 0.419 ₹0.00 ₹0.00
Planks = 1.6 cum.
Battens = 1.75 cum.
Total = 3.35 cum.
Qty taken for cost of using once = 3.35/8 = 0.419 cum
LABOUR
For assembling erection dismantling & cleaning.
0112 Carpenter 2nd class day 10 ₹816.00 ₹8,160.00
0114 Beldar day 7.5 ₹736.00 ₹5,520.00
9999 Sundries L.S. 65 ₹2.27 ₹147.55

Rate build-up

TOTAL ₹24,716.35
Add 1 % Water charges on "W" ₹247.16
TOTAL ₹24,963.51
Add GST on "X" (multiplying factor 0.2127) ₹5,309.74
TOTAL ₹30,273.25
Add 15% CPOH on "Y" ₹4,540.99
TOTAL ₹34,814.24
Add Cess @ 1% on "Z" ₹348.14
Cost of 40 sqm. ₹35,162.38
Cost of 1 sqm. ₹879.06
Say ₹879.05

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook