DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.16.1 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls Under 20 cm wide

Published rate₹208.55DSR 2023
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls

DSR rate₹208.55as per item analysis

Under 20 cm wide

Item code
5.9.16.1
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
See analysis
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10Nos of 3mx3m slab 15cms thick
120 m edge Length
MATERIAL
Assuming that the timber will become unserviceable after being used 8 times.
1198 Second class kail wood in planks 10 cudm 7.125 ₹260.00 ₹1,852.50
(i) Planks 30mm thick (2nd class Kail wood
or equivalent local soft wood)
10x4x3x0.15x0.030=0.54 cum
Wastage @5% = 0.03 cum.
Total = 0.57 cum 570 cudm
Qty taken for cost of using once = 570/8 =71.25 cudm
1197 Second class kail wood in scantling 10 cudm 19.375 ₹260.00 ₹5,037.50
(ii) Battens 75mmx100mm (2nd class Kail wood)
Horizontal 10x2x4x0.075x0.1x0.5=0.30
Horizontal 10x2x4x0.075x0.1x1.5=0.90
(iii) Vertical battens
10x16x0.15x0.075x0.030m = 0.054
(iv) Struts
10x16x0.25x0.075x0.075=0.225
Total = 1.479
Wastage @5% = 0.074
Total = 1.553 cum = 1550 cudm say
Qty taken for cost ef using once = 1550/8 =193.75 cudm
2204 Carriage of Timber cum 0.265 ₹0.00 ₹0.00
Planks = 0.57 cum.
Battens = 1.55 cum.
Total = 2.12 cum.
Qty taken for cost of using once = 2.12/8 = 0.265 cum
LABOUR
For assembling erection dismantling & cleaning.
0112 Carpenter 2nd class day 8.1 ₹816.00 ₹6,609.60
0114 Beldar day 5.4 ₹736.00 ₹3,974.40
9999 Sundries L.S. 52 ₹2.27 ₹118.04

Rate build-up

TOTAL ₹17,592.04
Add 1 % Water charges on "W" ₹175.92
TOTAL ₹17,767.96
Add GST on "X" (multiplying factor 0.2127) ₹3,779.25
TOTAL ₹21,547.21
Add 15% CPOH on "Y" ₹3,232.08
TOTAL ₹24,779.29
Add Cess @ 1% on "Z" ₹247.79
Cost of 120 metre ₹25,027.08
Cost of one metre ₹208.56
Say ₹208.55