DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.10 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Extra for arches, domes, vaults exceeding 6 m span

Published rate₹608.15per sqm of soffit area
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for

DSR rate₹608.15per sqm of soffit area

Extra for arches, domes, vaults exceeding 6 m span

Item code
5.9.10
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
sqm of soffit area
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 333.1 sqm
Centering and shuttering for 10 Nos. arches and carved surface exceeding 6m in span (an average of 8m)
Radius R = 5m 2R-2 = 8
tan -¹ (4/3)=53.28°
2x53.28° = 106°
Surface area =10x2x(22/7)x5x3.6x106/360 =333.10 sqm
Arc=9.25m
MATERIAL
Tie-2x8x0.18x0.05 =0.144cum
Struts-2x2.5x0.1x0.1 =0.050cum.
Struts-2x1.77x0.1x0.1=0.035cum.
Ribs-6x1.54x0.23x0.1=0.213cum.
Struts-2x1.72x0.1x0.1=0.034cum.
Total=0.476cum.
For 10x4 such frames =0.476x4x10 = 19.04 cum
laggings-10x75x3.6x0.125x0.075=25.31cum
Tie-10x2x3.6x0.225x0.038=0.62cum
Brace-10x3x2x2.14x0.225x0.038=1.10 cum
Brace-10x3x4x3.8x0.225x0.038=3.90 cum
Sleepers-10x4x3.6x0.20x0.15=4.32 cum
Sleepers-10x2x4x3.6x0.175x0.075=3.78 cum
Vertical post-10x4x4x3.6x0.15x0.15=12.96 cum
Total =71.03cum. or 71030 cudm
Qty taken 1/8th of qty for cost using once =71030/8 = 8879 Cudm
1197 Second class kail wood in scantling 10 cudm 887.9 ₹260.00 ₹2,30,854.00
2204 Carriage of Timber cum 8.879 ₹0.00 ₹0.00
Fittings:
3 way straps 50mmx10mm = 32x10 Nos. =320 Nos.
320 no. @0.50cm each = 160m
Straps-50mmx10mm = 8x10 Nos. @ 0.25cm each = 20m
Total = 180m
180m, wt @ 3.9kg/m = 702 kg. = 7.02q
Qty taken l/8th of qty for cost using once = 7.02/8 = 0.878
1225 Mild steel flat strap fitting quintal 0.878 ₹4,120.00 ₹3,617.36
Bolts 160x10 Nos. 254 mm long 16mm dia.-
1600x.254x 1.58=642.1 kg=6.42q.
Qty taken l/8th of qty for cost using once =6.42/8 = 0.802
1034 Bolts and nuts upto 300 mm in length quintal 0.802 ₹5,200.00 ₹4,170.40
2302 Carriage of G.I.sheet and accessories tonne 0.168 ₹0.00 ₹0.00
Qty taken 1/8th of qty for cost using once = 0.878+0.802=0.168 tonne
LABOUR
0112 Carpenter 2nd class day 280 ₹816.00 ₹2,28,480.00
0114 Beldar day 240 ₹736.00 ₹1,76,640.00
9999 Sundries L.S. 1,345.5 ₹2.27 ₹3,054.29
Less Cost of shuttering etc. for an arch exceeding 6 m span i.e. for an average of 8 m span
5.9.9 Rate as per item no 5.9.9 of SH : RCC sqm -333.1 ₹2,154.35 -₹7,17,613.99

Rate build-up

TOTAL -₹70,797.94
Add 1 % Water charges on "W-A" ₹6,468.16
TOTAL -₹64,329.78
Add GST on "X-A" (multiplying factor 0.2127) ₹1,38,953.55
TOTAL ₹74,623.77
Add 15% CPOH on "Y-A" ₹1,18,835.66
TOTAL ₹1,93,459.43
Add Cess @ 1% on "Z-A" ₹9,110.73
Cost of 333.1sqm. ₹2,02,570.16
Cost per sqm of soffit area ₹608.14
Say ₹608.15

Use this rate in the interactive workbook