Rate analysis
Reinforced cement concrete work in chimneys, shafts, up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
DSR rate₹11,125.20as per item analysis
- Item code
- 5.6
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- See analysis
- Source row
- 428
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| RCC 1:1½:3 in chimneys & shafts | |||||
| 5.2.2 | Rate as per Item No.5.2.2 of SH: REINFORCED CEMENT CONCRETE | cum | 1 | ₹10,852.95 | ₹10,852.95 |
| LABOUR | |||||
| Extra labour involved for laying cc in chimneys,shafts | |||||
| 0115 | Coolie | day | 0.26 | ₹736.00 | ₹191.36 |
Rate build-up
| TOTAL | ₹11,044.31 |
| Add 1 % Water charges on "W-A" | ₹1.91 |
| TOTAL | ₹11,046.22 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹41.11 |
| TOTAL | ₹11,087.33 |
| Add 15% CPOH on "Y-A" | ₹35.16 |
| TOTAL | ₹11,122.49 |
| Add Cess @ 1% on "Z-A" | ₹2.70 |
| Cost for 1 cum. | ₹11,125.19 |
| Say | ₹11,125.20 |