Rate analysis
Steel reinforcement for R.C.C. work ready to use "cut and bend" rebars of approved make from factory/workshop to construction site including placing in position and binding all complete above plinth level.
DSR rate₹99.65per Kg
Thermo-Mechanically Treated bars of grade Fe-500D or more.
- Item code
- 5.22C.1
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- Kg
- Source row
- 2732
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 quintal- | |||||
| MATERIAL | |||||
| Deformed twisted steel bars = 1.00 q | |||||
| 1005 | Twisted steel / deformed bars | quintal | 1 | ₹5,550.00 | ₹5,550.00 |
| 2205 | Carriage of steel 1.0/10 = 0.1t | tonne | 0.1 | ₹0.00 | ₹0.00 |
| 9999 | Cover block | L.S. | 26 | ₹2.27 | ₹59.02 |
| LABOUR | |||||
| 9999 | For cut and bend | L.S. | 156 | ₹2.27 | ₹354.12 |
| For binding and placing in position | |||||
| 0102 | Blacksmith 1st class | day | 0.6 | ₹897.00 | ₹538.20 |
| 0114 | Beldar | day | 0.6 | ₹736.00 | ₹441.60 |
| 9999 | Sundries and binding wire | L.S. | 26.91 | ₹2.27 | ₹61.09 |
Rate build-up
| TOTAL | ₹7,004.03 |
| Add 1 % Water charges | ₹70.04 |
| TOTAL | ₹7,074.07 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,504.65 |
| TOTAL | ₹8,578.72 |
| Add 15% CPOH on "Y" | ₹1,286.81 |
| TOTAL | ₹9,865.53 |
| Add Cess @1% on "Z" | ₹98.66 |
| Cost of one quintal | ₹9,964.19 |
| Cost of 1 Kg. | ₹99.64 |