DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.22B.1 rate analysis

Steel reinforcement for R.C.C. work ready to use "cut and bend" rebars of approved make from factory/workshop to construction site including placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more.

Published rate₹99.65per Kg
Rate analysis

Steel reinforcement for R.C.C. work ready to use "cut and bend" rebars of approved make from factory/workshop to construction site including placing in position and binding all complete upto plinth level.

DSR rate₹99.65per Kg

Thermo-Mechanically Treated bars of grade Fe-500D or more.

Item code
5.22B.1
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
Kg
Source row
2702

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
1005 Twisted steel / deformed bars quintal 1 ₹5,550.00 ₹5,550.00
2205 Carriage of steel 1.0/10 = 0.1t tonne 0.1 ₹0.00 ₹0.00
9999 Cover block L.S. 26 ₹2.27 ₹59.02
LABOUR
9999 For cut and bend L.S. 156 ₹2.27 ₹354.12
For binding and placing in position
0102 Blacksmith 1st class day 0.6 ₹897.00 ₹538.20
0114 Beldar day 0.6 ₹736.00 ₹441.60
9999 Sundries and binding wire L.S. 26.91 ₹2.27 ₹61.09

Rate build-up

TOTAL ₹7,004.03
Add 1 % Water charges ₹70.04
TOTAL ₹7,074.07
Add GST on "X" (multiplying factor 0.2127) ₹1,504.65
TOTAL ₹8,578.72
Add 15% CPOH on "Y" ₹1,286.81
TOTAL ₹9,865.53
Add Cess @1% on "Z" ₹98.66
Cost of one quintal ₹9,964.19
Cost of 1 Kg. ₹99.64
Say ₹99.65

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook