Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand incuding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) including centering and shuttering complete but excluding cost of reinforcement.

Published rate₹15,918.60per cum
Rate analysis

Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand incuding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) including centering and shuttering complete but excluding cost of reinforcement.

DSR rate₹15,918.60per cum
Item code
5.19A
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
cum
Source row
2269

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 0.424 cum
Consider 2 R.S. Joists (150mmx80mm) 4.88m long placed 30cm apart centre to centre
Overall dimensions of the beam 43cmx20cm
MATERIAL:
Concrete work :4.93x0.43x0.20 = 0.424 cum
For 1:1.5:3 Cement Concrete (1 cement: 1½ coarse sand (RCA) upto 20% : 3 stone aggregate 20mm nominal size (RCA) upto 20%)
Sub AR-1 Rate as per sub AR-1 (Ref item no 4.1.2) cum 0.424 ₹8,170.05 ₹3,464.10
Extra labour for laying C.C. in RCC work
0114 Beldar day 0.042 ₹736.00 ₹30.91
0101 Bhisti day 0.085 ₹816.00 ₹69.36
0123 Mason 1st class day 0.017 ₹897.00 ₹15.25
0124 Mason 2nd class day 0.017 ₹816.00 ₹13.87
0128 Mate day 0.017 ₹816.00 ₹13.87
Form work-4.93x0.83 girth = 4.09 sqm
5.9.5 Rate as per Item Number 5.9.5 of SH: Reinforced cement concrete work sqm 4.09 ₹736.40 ₹3,011.88
9999 Sundries and for lifting materials L.S. 21.58 ₹2.27 ₹48.99

Rate build-up

Total ₹6,668.23
Add 1 % Water charges on "W-A" ₹1.92
TOTAL ₹6,670.15
Add GST on "X-A" (multiplying factor 0.2127) ₹41.30
TOTAL ₹6,711.45
Add 15% CPOH on "Y-A" ₹35.32
TOTAL ₹6,746.77
Add Cess @ 1% on "Z-A" ₹2.71
Cost of 0.424 cum ₹6,749.48
Cost of 1 cum ₹15,918.58
Say ₹15,918.60