DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.6.1 rate analysis

Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering complete. 1:1½:3 (1 Cement: 1½ coarse sand(zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources).

Published rate₹8,726.85per cum
Rate analysis

Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering complete.

DSR rate₹8,726.85per cum

1:1½:3 (1 Cement: 1½ coarse sand(zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources).

Item code
4.6.1
Sub-head
SH 4 · CONCRETE WORK
Unit
cum
Source row
1159

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 250 no kerbs, 40x30x20cm
250 no x 0.40m x 0.30m x 0.20m = 6 cum
MATERIAL
Cement concrete 1:1.5:3
4.1.2 Rate as per Item No.4.1.2 of SH:CONCRETE WORK cum 6 ₹8,340.85 ₹50,045.10
Centering and shuttering
(1) Mould
(i) Plate 3mm thick
10x0.28 sqm. @ 23.55kg/m² = 65.9 kg.
(ii) Flat 10x5mm
Handle
10x2x0.25 x0.4 = 2kg. Total =67.9 kg
Assuming shuttering will become unserviceable after use of 40 times and taking 75% credit.
Qty taken for cost of using once = 67.9x0.75/40 = 1.273 kg
10.1 Rate as per item no 10.1 SH: Steel work kg 1.273 ₹117.35 ₹149.39
(2) Moulding Platform
Assuming platform will become unserviceable after use of 40 times.
(i) Brick on edge flooring cement mortar 1:6
10x1x2.0x2.0m = 40 sqm.
Qty taken for cost of using once = 40/40 = 1 sqm
11.1.2 Rate as per item no. 11.1.2 S.H: Flooring work. sqm 1 ₹965.55 ₹965.55
(ii) 25mm thick cement concrete 1:2:4 in pavement
10x2.00x2.00x0.025 = 1
Qty taken for cost of using once = 1/40 = 0.025 cum
11.7 Rate as per Item Number 11.7 of SH: Flooring cum 0.025 ₹8,595.15 ₹214.88
9999 Mortar and labour for finishing L.S. 305.4 ₹2.27 ₹693.26

Rate build-up

TOTAL ₹52,068.18
Add 1 % Water charges on "W-A" ₹6.93
TOTAL ₹52,075.11
Add GST on "X-A" (multiplying factor 0.2127) ₹148.93
TOTAL ₹52,224.04
Add 15% CPOH on "Y-A" ₹127.37
TOTAL ₹52,351.41
Add Cess @ 1% on "Z-A" ₹9.76
Cost for 6 cum. ₹52,361.17
Cost per cum. ₹8,726.86
Say ₹8,726.85

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook