DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.5.1A rate analysis

Providing and fixing up to floor five level precast cement concrete string or lacing courses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering complete. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%))

Published rate₹8,844.45per Cum
Rate analysis

Providing and fixing up to floor five level precast cement concrete string or lacing courses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering complete.

DSR rate₹8,844.45per Cum

1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%))

Item code
4.5.1A
Sub-head
SH 4 · CONCRETE WORK
Unit
Cum
Source row
1042

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for Plain window sill 10x15 nos.
10x15x1m x 0.20m x 0.15m = 4.5cum.
MATERIAL
Cement concrete 1:1½:3
4.1.2A Rate as per Item Number 4.1.2A of SH: Concrete work cum 4.5 ₹8,127.80 ₹36,575.10
0115 Coolie day 5.1 ₹736.00 ₹3,753.60
(Extra labour for lifting = 0.75 x 4.5 x 1.5 = 5.1)
Centering and shuttering
(1) Mould
(i) Plate 3mm thick
[(2x1x0.15)+(2x0.15x0.20)]x10 = 3.6 sqm. @ 23.55kg/m² = 84.8 kg.
(ii) Flat 10x5mm
10x4x1.0 = 40m
10x8x0.2 = 16m
10x4x0.15 = 6m
Handle 10x2x0.25 = 5m
67m @ 0.4kg/m = 26.8 kg.
Total = 111.6kg
Assuming shuttering will become unserviceable after use of 40 times and taking 75% credit.
Qty taken for cost of using once = 111.6x0.75/40 = 2.1 kg
10.1 Rate as per item no.10.1 S.H. steel work kg 2.1 ₹117.35 ₹246.44
(2) Moulding Platform
Assuming platform will become
unserviceable after use of 40 times.
(i) Brick on edge flooring cement mortar 1:6
10x1x2.0x2.0m = 40 sqm.
Qty taken for cost of using once = 40/40 = 1 sqm
11.1.2 Rate as per item no. 11.1.2 of S.H.: Flooring work sqm 1 ₹965.55 ₹965.55
(ii) 25mm thick cement concrete 1:2:4 in pavement
10x2.00x2.00x0.025 = 1cum
Qty taken for cost of using once = 1/40 = 0.025 cum
Sub A/R-1 Rate as per item no. Sub AR-1 (Reference item no 11.7) cum 0.025 ₹8,844.45 ₹221.11
9999 Mortar and labour for hoisting and finishing L.S. 363 ₹2.27 ₹824.01
Sub AR-1 (Reference item no 11.7) Cement concrete pavement with 1:1.5:3 (1 cement : 1.5 coarse sand including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%), including finishing complete.
Details of cost for one cum.
MATERIAL
Cement concrete 1:1.5:3
4.1.2A Rate as per item No.4.1.2A of S.H.Concrete Work cum 1 ₹8,127.80 ₹8,127.80
Extra labour for laying in floors etc.
0124 Mason (brick layer) 2nd class day 0.35 ₹816.00 ₹285.60
0114 Beldar day 0.18 ₹736.00 ₹132.48
0101 Bhisti day 0.05 ₹816.00 ₹40.80
9999 Sundries L.S. 19.76 ₹2.27 ₹44.86

Rate build-up

TOTAL ₹42,585.81
Add 1 % Water charges on "W-A" ₹45.78
TOTAL ₹42,631.59
Add GST on "X-A" (multiplying factor 0.2127) ₹983.40
TOTAL ₹43,614.99
Add 15% CPOH on "Y-A" ₹841.02
TOTAL ₹44,456.01
Add Cess @ 1% on "Z-A" ₹64.48
Cost for 4.5 cum. ₹44,520.49
Cost per cum. ₹9,893.44
Say ₹9,893.45
TOTAL ₹8,631.54
Add 1 % Water charges on "W-A" ₹5.04
TOTAL ₹8,636.58
Add GST on "X-A" (multiplying factor 0.2127) ₹108.22
TOTAL ₹8,744.80
Add 15% CPOH on "Y-A" ₹92.55
TOTAL ₹8,837.35
Add Cess @ 1% on "Z-A" ₹7.10
Cost of 1 Cum. ₹8,844.45
Say ₹8,844.45

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook