DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.2.2A rate analysis

Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:1½:3 (1 cement : 1½ coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%) ).

Published rate₹10,144.50per cum
Rate analysis

Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:

DSR rate₹10,144.50per cum

1:1½:3 (1 cement : 1½ coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%) ).

Item code
4.2.2A
Sub-head
SH 4 · CONCRETE WORK
Unit
cum
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
0295 Stone Aggregate (Single size) 20 mm nominal size derived from natural sources cum 0.428 ₹1,425.00 ₹609.90
0279 Recycled Concrete Aggregate (RCA) 20 mm nominal size cum 0.142 ₹957.00 ₹135.89
0297 Stone Aggregate (Single size) 10 mm nominal size derived from natural sources cum 0.21 ₹1,400.00 ₹294.00
0281 Recycled Concrete Aggregate (RCA): 10 mm nominal size cum 0.07 ₹957.00 ₹66.99
2202 Carriage of Stone aggregate including Recycled Concrete Aggregate (RCA) below 40 mm nominal size cum 0.85 ₹0.00 ₹0.00
0982 Coarse sand (zone III) derived from natural sources cum 0.319 ₹1,450.00 ₹462.55
0278 Manufactured sand derived from Recycled Concrete Aggregate (RCA) cum 0.106 ₹957.00 ₹101.44
2203 Carriage of Coarse sand including manufactured sand cum 0.425 ₹0.00 ₹0.00
0367 Portland Cement (0.2833 cum) tonne 0.4 ₹5,156.00 ₹2,062.40
2209 Carriage of Cement tonne 0.4 ₹0.00 ₹0.00
LABOUR
0114 Beldar day 0.9 ₹736.00 ₹662.40
0115 Coolie day 0.78 ₹736.00 ₹574.08
0101 Bhisti day 0.7 ₹816.00 ₹571.20
0123 Mason (brick layer) 1st class day 0.06 ₹897.00 ₹53.82
0124 Mason (brick layer) 2nd class day 0.06 ₹816.00 ₹48.96
0002 Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper day 0.07 ₹900.00 ₹63.00
0012 Vibrator(Needle type 40mm) day 0.07 ₹400.00 ₹28.00
9999 Scaffolding L.S. 114.4 ₹2.27 ₹259.69
9999 Sundries L.S. 14.3 ₹2.27 ₹32.46
(Extra labour for lifting material upto floor V level = 0.75 x 2.0 = 1.50)
0115 Coolie day 1.5 ₹736.00 ₹1,104.00

Rate build-up

TOTAL ₹7,130.78
Add 1 % Water charges on "W" ₹71.31
TOTAL ₹7,202.09
Add GST on "X" (multiplying factor 0.2127) ₹1,531.88
TOTAL ₹8,733.97
Add 15% CPOH on "Y" ₹1,310.10
TOTAL ₹10,044.07
Add Cess @ 1% on "Z" ₹100.44
Cost of 1 cum. ₹10,144.51
Say ₹10,144.50