DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.1.4 rate analysis

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 40 mm nominal size derived from natural sources)

Published rate₹7,780.30per cum
Rate analysis

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :

DSR rate₹7,780.30per cum

1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 40 mm nominal size derived from natural sources)

Item code
4.1.4
Sub-head
SH 4 · CONCRETE WORK
Unit
cum
Source row
4

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
0293 Stone Aggregate (Single size) : 40 mm nominal size, cum 0.52 ₹1,400.00 ₹728.00
0.56 - (7.5% for voids i.e.) 0.04 = 0.52 cum
0295 Stone Aggregate (Single size) : 20 mm nominal size cum 0.22 ₹1,425.00 ₹313.50
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 0.11 ₹1,400.00 ₹154.00
2206 Carriage of Stone aggregate 40 mm nominal size and above cum 0.52 ₹0.00 ₹0.00
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.33 ₹0.00 ₹0.00
0982 Coarse sand (zone III) cum 0.445 ₹1,450.00 ₹645.25
2203 Carriage of Coarse sand cum 0.445 ₹0.00 ₹0.00
0367 Portland Cement (0.2225 cum) tonne 0.32 ₹5,156.00 ₹1,649.92
2209 Carriage of Cement tonne 0.32 ₹0.00 ₹0.00
LABOUR
0155 Mason (average) day 0.1 ₹857.00 ₹85.70
0114 Beldar day 1.63 ₹736.00 ₹1,199.68
0101 Bhisti day 0.7 ₹816.00 ₹571.20
0002 Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper day 0.07 ₹900.00 ₹63.00
0012 Vibrator(Needle type 40mm) day 0.07 ₹400.00 ₹28.00
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹5,468.94
Add 1 % Water charges on "W" ₹54.69
TOTAL ₹5,523.63
Add GST on "X" (multiplying factor 0.2127) ₹1,174.88
TOTAL ₹6,698.51
Add 15% CPOH on "Y" ₹1,004.78
TOTAL ₹7,703.29
Add Cess @ 1% on "Z" ₹77.03
Cost of 1 cum. ₹7,780.32
Say ₹7,780.30