Rate analysis
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
DSR rate₹8,340.85per cum
1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
- Item code
- 4.1.2
- Sub-head
- SH 4 · CONCRETE WORK
- Unit
- cum
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 0295 | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.57 | ₹1,425.00 | ₹812.25 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.28 | ₹1,400.00 | ₹392.00 |
| 2202 | Carriage of Stone aggregate below 40 mm nominal size | cum | 0.85 | ₹0.00 | ₹0.00 |
| 0982 | Coarse sand (zone III) | cum | 0.425 | ₹1,450.00 | ₹616.25 |
| 2203 | Carriage of Coarse sand | cum | 0.425 | ₹0.00 | ₹0.00 |
| 0367 | Portland Cement (0.2833 cum) | tonne | 0.4 | ₹5,156.00 | ₹2,062.40 |
| 2209 | Carriage of Cement | tonne | 0.4 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 0.1 | ₹857.00 | ₹85.70 |
| 0114 | Beldar | day | 1.63 | ₹736.00 | ₹1,199.68 |
| 0101 | Bhisti | day | 0.7 | ₹816.00 | ₹571.20 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper | day | 0.07 | ₹900.00 | ₹63.00 |
| 0012 | Vibrator(Needle type 40mm) | day | 0.07 | ₹400.00 | ₹28.00 |
| 9999 | Sundries | L.S. | 14.3 | ₹2.27 | ₹32.46 |
Rate build-up
| TOTAL | ₹5,862.94 |
| Add 1 % Water charges on "W" | ₹58.63 |
| TOTAL | ₹5,921.57 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,259.52 |
| TOTAL | ₹7,181.09 |
| Add 15% CPOH on "Y" | ₹1,077.16 |
| TOTAL | ₹8,258.25 |
| Add Cess @ 1% on "Z" | ₹82.58 |
| Cost of 1 cum. | ₹8,340.83 |
| Say | ₹8,340.85 |