Rate analysis
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
DSR rate₹6,311.95as per item analysis
1:2½:4:11 (1 ordinary portland cement : 2½ fly ash : 4 coarse sand(zone-III) derived from natural sources : 11 graded stone aggregate 40 mm nominal size derived from natural sources)
- Item code
- 4.1.13
- Sub-head
- SH 4 · CONCRETE WORK
- Unit
- See analysis
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 0293 | Stone Aggregate (Single size) : 40 mm nominal size | cum | 0.65 | ₹1,400.00 | ₹910.00 |
| (0.70 cum-7.5% for voids i.e. 0.05 = 0.65 cum) | |||||
| 0295 | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.24 | ₹1,425.00 | ₹342.00 |
| 2206 | Carriage of Stone aggregate 40 mm nominal size and above | cum | 0.65 | ₹0.00 | ₹0.00 |
| 2202 | Carriage of Stone aggregate below 40 mm nominal size | cum | 0.24 | ₹0.00 | ₹0.00 |
| 0982 | Coarse sand (zone III) | cum | 0.34 | ₹1,450.00 | ₹493.00 |
| 2203 | Carriage of Coarse sand | cum | 0.34 | ₹0.00 | ₹0.00 |
| 1980 | Flyash | cum | 0.21 | ₹12.00 | ₹2.52 |
| 2262 | Carriage of Flyash | cum | 0.21 | ₹185.55 | ₹38.97 |
| 0367 | Portland Cement | tonne | 0.13 | ₹5,156.00 | ₹670.28 |
| 2209 | Carriage of Cement | tonne | 0.13 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 0.1 | ₹857.00 | ₹85.70 |
| 0114 | Beldar | day | 1.63 | ₹736.00 | ₹1,199.68 |
| 0101 | Bhisti | day | 0.7 | ₹816.00 | ₹571.20 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper | day | 0.07 | ₹900.00 | ₹63.00 |
| 0012 | Vibrator(Needle type 40mm) | day | 0.07 | ₹400.00 | ₹28.00 |
| 9999 | Sundries | L.S. | 14.3 | ₹2.27 | ₹32.46 |
Rate build-up
| TOTAL | ₹4,436.81 |
| Add 1 % Water charges on "W" | ₹44.37 |
| TOTAL | ₹4,481.18 |
| Add GST on "X" (multiplying factor 0.2127) | ₹953.15 |
| TOTAL | ₹5,434.33 |
| Add 15% CPOH on "Y" | ₹815.15 |
| TOTAL | ₹6,249.48 |
| Add Cess @ 1% on "Z" | ₹62.49 |
| Cost of one cum. | ₹6,311.97 |
| Say | ₹6,311.95 |