DSR 2023 · SH 3 · MORTARS

CPWD DSR item 3.19 rate analysis

Mortar in lime, surkhi (50% red and 50% light yellow) and marble dust 1:1.5:0.5

Published rate₹2,880.65DSR 2023
Rate analysis

Mortar in lime, surkhi (50% red and 50% light yellow) and marble dust 1:1.5:0.5

DSR rate₹2,880.65as per item analysis
Item code
3.19
Sub-head
SH 3 · MORTARS
Unit
See analysis
Source row
322

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum
MATERIAL
(0.475 cum of lime putty) = 3.01 q of unslaked lime
1182 Surkhi cum 7.125 ₹778.00 ₹5,543.25
0773 Unslaked lime quintal 30.1 ₹325.00 ₹9,782.50
0784 Marble dust/ powder cum 2.4 ₹1,180.00 ₹2,832.00
2268 Marble dust and/or marble chips cum 2.4 ₹0.00 ₹0.00
2208 Carriage of Lime cum 30.1 ₹0.00 ₹0.00
LABOUR
For slaking lime, making lime putty, grinding and carrying
0114 Beldar day 9 ₹736.00 ₹6,624.00
0101 Bhisti day 4.5 ₹816.00 ₹3,672.00
9999 As cost for running and upkeep of mortar mill L.S. 103.5 ₹2.27 ₹234.95
9999 Sundries L.S. 52 ₹2.27 ₹118.04

Rate build-up

Cost of 10.00 cum ₹28,806.74
Cost of 1.00 cum ₹2,880.67
Say ₹2,880.65