DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.96.1 rate analysis

Providing and placing "Stay in Place PVC Wall formwork" made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge. (Note: Suitable for in fill walls with appropriate Structural system). 125 mm wide Stay in Place PVC Wallform made of minimum 2.50 mm thick sections and minimum weight 21.97 kg /sqm of formwork.

Published rate₹2,926.70DSR 2023
Rate analysis

Providing and placing "Stay in Place PVC Wall formwork" made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge.

DSR rate₹2,926.70as per item analysis

(Note: Suitable for in fill walls with appropriate Structural system).

125 mm wide Stay in Place PVC Wallform made of minimum 2.50 mm thick sections and minimum weight 21.97 kg /sqm of formwork.

Item code
26.96.1
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
See analysis
Source row
5270

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 20 sqm surface area
MATERIAL
8996 125 mm wide Stay in Place Wallform 2.50 mm thick of extruded Unplasticised Poly Vinyl Chloride (uPVC).
Cost of Raw Materials for 20/2 = 10 sqm of 125 mm Wallforms @21.97 kg/sqm 219.70 kg + 5% wastage (10.98 kg) = 230.68 kg kg 230.68 ₹160.00 ₹36,908.80
9999 Transportation Charges L.S. 610.38 ₹2.27 ₹1,385.56
Labour for Installation
0123 Mason 1st Class day 1 ₹897.00 ₹897.00
0115 Beldar day 2.5 ₹736.00 ₹1,840.00
9999 Sundries L.S. 50 ₹2.27 ₹113.50

Rate build-up

TOTAL ₹41,144.86
Add 1% Water charges on "W" ₹411.45
TOTAL ₹41,556.31
Add GST on "X" (multiplying factor 0.2127) ₹8,839.03
TOTAL ₹50,395.34
Add 15% CPOH on "Y" ₹7,559.30
TOTAL ₹57,954.64
Add Cess @ 1% on "Z" ₹579.55
Cost of 20 sqm ₹58,534.19
Cost for 1 sqm ₹2,926.71
Say ₹2,926.70

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook