Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor. Prestressed hollow core slab above 200 mm up to 400 mm thickness

Published rate₹345.15per Sqm
Rate analysis

Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor.

DSR rate₹345.15per Sqm

Prestressed hollow core slab above 200 mm up to 400 mm thickness

Item code
26.77.2
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
Sqm
Source row
4059

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 120 Sqm.
Length of element can be more than 8.00 metre and upto 14.00 metres.
0067 Cost for crane upto 80 tonne capacity day 1 ₹16,800.00 ₹16,800.00
9999 Hire charges of props & Misc L.S. 347 ₹2.27 ₹787.69
0070 Genrator hiring 100kva hour 8 ₹350.00 ₹2,800.00
Labour cost for erection
0111 Carpenter 1st class day 1 ₹897.00 ₹897.00
0112 Carpenter 2nd class day 2 ₹816.00 ₹1,632.00
0116 Fitter (grade 1) day 2 ₹897.00 ₹1,794.00
0130 Mistry day 2 ₹897.00 ₹1,794.00
0114 Beldar day 2 ₹736.00 ₹1,472.00
9999 Sundries (Miscellaneous tools and lifting slings) L.S. 500 ₹2.27 ₹1,135.00

Rate build-up

TOTAL ₹29,111.69
Add 1 % Water charges on "W" ₹291.12
TOTAL ₹29,402.81
Add GST on "X" (multiplying factor 0.2127) ₹6,253.98
TOTAL ₹35,656.79
Add 15% CPOH on "Y" ₹5,348.52
TOTAL ₹41,005.31
Add Cess @ 1% on "Z" ₹410.05
Cost for 120 Sqm ₹41,415.36
Cost of 1 Sqm ₹345.13
Say ₹345.15