Rate analysis
Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor.
DSR rate₹345.15per Sqm
Prestressed hollow core slab above 200 mm up to 400 mm thickness
- Item code
- 26.77.2
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- Sqm
- Source row
- 4059
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 120 Sqm. | |||||
| Length of element can be more than 8.00 metre and upto 14.00 metres. | |||||
| 0067 | Cost for crane upto 80 tonne capacity | day | 1 | ₹16,800.00 | ₹16,800.00 |
| 9999 | Hire charges of props & Misc | L.S. | 347 | ₹2.27 | ₹787.69 |
| 0070 | Genrator hiring 100kva | hour | 8 | ₹350.00 | ₹2,800.00 |
| Labour cost for erection | |||||
| 0111 | Carpenter 1st class | day | 1 | ₹897.00 | ₹897.00 |
| 0112 | Carpenter 2nd class | day | 2 | ₹816.00 | ₹1,632.00 |
| 0116 | Fitter (grade 1) | day | 2 | ₹897.00 | ₹1,794.00 |
| 0130 | Mistry | day | 2 | ₹897.00 | ₹1,794.00 |
| 0114 | Beldar | day | 2 | ₹736.00 | ₹1,472.00 |
| 9999 | Sundries (Miscellaneous tools and lifting slings) | L.S. | 500 | ₹2.27 | ₹1,135.00 |
Rate build-up
| TOTAL | ₹29,111.69 |
| Add 1 % Water charges on "W" | ₹291.12 |
| TOTAL | ₹29,402.81 |
| Add GST on "X" (multiplying factor 0.2127) | ₹6,253.98 |
| TOTAL | ₹35,656.79 |
| Add 15% CPOH on "Y" | ₹5,348.52 |
| TOTAL | ₹41,005.31 |
| Add Cess @ 1% on "Z" | ₹410.05 |
| Cost for 120 Sqm | ₹41,415.36 |
| Cost of 1 Sqm | ₹345.13 |
| Say | ₹345.15 |