DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.6A rate analysis

Providing, erecting, laying and fixing in position in 3.5 to 4 mm thick bamboo mat corrugated sheet (BMCS) as per IS: 15476-2004 in roofing with self drilling screws along with EPDM washers complete or with galvanized iron J or L hooks 8mm dia G.I. plain and bitumen washers etc, all complete as per direction of Engineer-in-Charge.

Published rate₹6,012.10DSR 2023
Rate analysis

Providing, erecting, laying and fixing in position in 3.5 to 4 mm thick bamboo mat corrugated sheet (BMCS) as per IS: 15476-2004 in roofing with self drilling screws along with EPDM washers complete or with galvanized iron J or L hooks 8mm dia G.I. plain and bitumen washers etc, all complete as per direction of Engineer-in-Charge.

DSR rate₹6,012.10as per item analysis
Item code
26.6A
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
See analysis
Source row
181

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 181.30sqm area.
Consider a sheet of 18mx9m (external dimension of plinth). Area of roof = 18.5x9.8m = 181.30 sqm.
MATERIAL:
Sheets used = 2x 19 nos (2.44m x 1.05m) & 4x19 nos (1.83mx 1.05m). Total area = (2x19x2.44x1.05)+(4x19x1.83x1.05) = 243.39sqm, Add wastage @ 3% = 7.30 sqm, Total area = 250.69 sqm.
8144 Bamboo Mat corrugated sheets 3.5 to 4mm thick conforming to IS 15476:2004 sqm 250.69 ₹2,891.00 ₹7,24,744.79
Weight of sheets, For 2.44mx1.05m sheet size, 12kg/Nos x 38 nos = 456 kgs, For 1.83m x 1.05m sheet size, 9kgs/Nos x 76 Nos = 684 kgs. Total weight of sheet = 456+684 = 1140 kgs = 1.14 tonne
2358 Carriage of Bamboo Mat corrugated sheets and accessories tonne 1.14 ₹17,700.00 ₹20,178.00
1023 Galvanized steel J or L hooks 8mm dia 10 Nos 68.4 ₹130.00 ₹8,892.00
1208 Bitumen washer 100 Nos 6.84 ₹30.00 ₹205.20
1209 G.I. plain washer thick 100 Nos 6.84 ₹35.00 ₹239.40
9977 Carriage of bolts and washers L.S. 11.58 ₹2.27 ₹26.29
9999 Sundries L.S. 56.78 ₹2.27 ₹128.89
LABOUR:
0130 Mistry day 3 ₹897.00 ₹2,691.00
0112 Carpenter 2nd class day 3 ₹816.00 ₹2,448.00
0114 Beldar day 9 ₹736.00 ₹6,624.00

Rate build-up

TOTAL ₹7,66,177.57
Add 1 % Water charges on "W" ₹7,661.78
TOTAL ₹7,73,839.35
Add GST on "X" (multiplying factor 0.2127) ₹1,64,595.63
TOTAL ₹9,38,434.98
Add 15% CPOH on "Y" ₹1,40,765.25
TOTAL ₹10,79,200.23
Add Cess @ 1% on "Z" ₹10,792.00
Cost of 181.30 sqm ₹10,89,992.23
Cost of 1sqm ₹6,012.09
Say ₹6,012.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.