CPWD DSR item 26.50.1 rate analysis

Non load bearing panels 50 mm thick of required size (minimum 4mm thick fibre cement board Type B, Category III as per IS: 14862:2000 on both faces )

Published rate₹2,068.25DSR 2023
Rate analysis

Non load bearing panels 50 mm thick of required size (minimum 4mm thick fibre cement board Type B, Category III as per IS: 14862:2000 on both faces )

DSR rate₹2,068.25as per item analysis
Item code
26.50.1
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
See analysis
Source row
2586

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost 10sqm (6.95Nos x0.6m x2.40m = 10sqm)
MATERIAL
Panel area = 10.00sqm, Add wastage @ 5% = 0.50sqm, Total area = 10.50 sqm
0244 Factory made light weight composite non asbestos fibre reinforced aerated cement sandwitched wall/roof panel (50mm thick). The outer face on both sides of the panels will be non asbestos fibre cement board (minimum 4mm thick) Type B, Category III as per IS 14862:2000 sqm 10.5 ₹650.00 ₹6,825.00
9999 Sundries, cement based polymer modified jointing compound, polymer based jointing compound having superior flexibility, fibre glass tape etc. L.S. 500 ₹2.27 ₹1,135.00
LABOUR
For fixing, aligning, locking the panels, glass fibre tape/fibre mesh with a jointing compound.
0123 Mason 1st class day 1 ₹897.00 ₹897.00
0114 Beldar day 2 ₹736.00 ₹1,472.00
0131 Painter day 0.5 ₹816.00 ₹408.00
26.50.1 A Non load bearing panels 50 mm thick of required size (minimum 4mm thick fibre cement board Type A, Category III as per IS: 14862:2000 on both faces )
Details of cost 10sqm (6.95 Nos x 0.6m x2.40m = 10sqm)
MATERIAL
Panel area = 10.00sqm, Add wastage @ 5% = 0.50sqm, Total area = 10.50 sqm
0253 Factory made light weight composite non asbestos fibre reinforced aerated cement sandwitched wall/roof panel (50mm thick). The outer face on both sides of the panels will be non asbestos fibre cement board (minimum 4mm thick) Type A, Category III confirming to IS 14862:2000 sqm 10.5 ₹722.00 ₹7,581.00
9999 Sundries, cement based polymer modified jointing compound, polymer based jointing compound having superior flexibility, fibre glass tape etc. L.S. 500 ₹2.27 ₹1,135.00
LABOUR
For fixing, aligning, locking the panels, glass fibre tape/fibre mesh with a jointing compound.
0123 Mason 1st class day 1 ₹897.00 ₹897.00
0114 Beldar day 2 ₹736.00 ₹1,472.00
0131 Painter day 0.5 ₹816.00 ₹408.00
26.50.1 B Non load bearing panels 50 mm thick of required size (minimum 4mm thick fibre cement board Type A, Category IV as per IS: 14862:2000 on both faces)
Details of cost 10sqm (6.95 Nos x 0.6m x2.40m = 10sqm)
MATERIAL
Panel area = 10.00sqm, Add wastage @ 5% = 0.50sqm, Total area = 10.50 sqm
0254 Factory made light weight composite non asbestos fibre reinforced aerated cement sandwitched wall/roof panel (50mm thick). The outer face on both sides of the panels will be non asbestos fibre cement board (minimum 4mm thick) Type A, Category IV confirming to IS 14862:2000 sqm 10.5 ₹1,012.00 ₹10,626.00
9999 Sundries, cement based polymer modified jointing compound, polymer based jointing compound having superior flexibility, fibre glass tape etc. L.S. 500 ₹2.27 ₹1,135.00
LABOUR
For fixing, aligning, locking the panels, glass fibre tape/fibre mesh with a jointing compound.
0123 Mason 1st class day 1 ₹897.00 ₹897.00
0114 Beldar day 2 ₹736.00 ₹1,472.00
0131 Painter day 0.5 ₹816.00 ₹408.00

Rate build-up

TOTAL ₹10,737.00
Add 1 % Water charges on "W" ₹107.37
TOTAL ₹10,844.37
Add GST on "X" (multiplying factor 0.2127) ₹2,306.60
TOTAL ₹13,150.97
Add 15% CPOH on "Y" ₹1,972.65
TOTAL ₹15,123.62
Add Cess @ 1% on "Z" ₹151.24
Cost of 10 sqm ₹15,274.86
Cost of 1sqm ₹1,527.49
Say ₹1,527.50
TOTAL ₹11,493.00
Add 1 % Water charges on "W" ₹114.93
TOTAL ₹11,607.93
Add GST on "X" (multiplying factor 0.2127) ₹2,469.01
TOTAL ₹14,076.94
Add 15% CPOH on "Y" ₹2,111.54
TOTAL ₹16,188.48
Add Cess @ 1% on "Z" ₹161.88
Cost of 10 sqm ₹16,350.36
Cost of 1sqm ₹1,635.04
Say ₹1,635.05
TOTAL ₹14,538.00
Add 1 % Water charges on "W" ₹145.38
TOTAL ₹14,683.38
Add GST on "X" (multiplying factor 0.2127) ₹3,123.15
TOTAL ₹17,806.53
Add 15% CPOH on "Y" ₹2,670.98
TOTAL ₹20,477.51
Add Cess @ 1% on "Z" ₹204.78
Cost of 10 sqm ₹20,682.29
Cost of 1sqm ₹2,068.23
Say ₹2,068.25