DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.25 rate analysis

Providing and fixing 15 mm thick false ceiling tiles at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991,in true horizontal level on the existing frame work consisting of T-sections and Lsections suitably fixed according to tile size as per direction of Engineer-in-charge.

Published rate₹1,781.20per sqm
Rate analysis

Providing and fixing 15 mm thick false ceiling tiles at all heights with integral densified calcium silicate reinforced with fibre and natural filler false ceiling tiles of Size 595x595 mm of approved texture, design and patterns having NRC (Noise Reduction coefficient) of 0.50 (minimum) as per IS 8225:1987, Light reflectance of 85% (minimum). Non combustible as per BS:476 (part-4), fire performance as per BS:476 (part 6 &7), humidity resistance of 100%, thermal conductivity < 0.043 W/m K as per ASTM 518:1991,in true horizontal level on the existing frame work consisting of T-sections and Lsections suitably fixed according to tile size as per direction of Engineer-in-charge.

DSR rate₹1,781.20per sqm
Item code
26.25
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
1234

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 Sqm
MATERIAL
8589 Calcium Silicate tegular edged celling tiles 595x595 mm and 15 mm thick sqm 10.5 ₹822.00 ₹8,631.00
10 + 0.5 (Add wastage @5%) = 10.5 sqm
9977 Carriage L.S. 14.95 ₹2.27 ₹33.94
LABOUR
0111 Carpenter 1st class day 2.5 ₹897.00 ₹2,242.50
0114 Beldar day 2 ₹736.00 ₹1,472.00
9999 Scaffolding L.S. 31.07 ₹2.27 ₹70.53
9999 Sundries L.S. 31.07 ₹2.27 ₹70.53

Rate build-up

TOTAL ₹12,520.50
Add 1 % Water charges on "W" ₹125.21
TOTAL ₹12,645.71
Add GST on "X" (multiplying factor 0.2127) ₹2,689.74
TOTAL ₹15,335.45
Add 15% CPOH on "Y" ₹2,300.32
TOTAL ₹17,635.77
Add Cess @ 1% on "Z" ₹176.36
Cost of 10 sqm ₹17,812.13
Cost of 1 sqm ₹1,781.21
Say ₹1,781.20

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook