Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/structure, upto 25 metre height, above ground level, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S. tube challis, M.S. clamps and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for execution of work of cleaning and/ or pointing and/ or applying chemical and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connecting with the building etc, wherever required, if feasible, for inspection of work at required locations with essential safety features for the workmen etc., complete as per directions and approval of Engineer-in-charge. Note:- (1) The elevational area of the scaffolding shall be measured for payment purpose. (2) The payment will be made once only for execution of all items for such works.
Published rate₹338.25DSR 2023
Rate analysis
Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/structure, upto 25 metre height, above ground level, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S. tube challis, M.S. clamps and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for execution of work of cleaning and/ or pointing and/ or applying chemical and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connecting with the building etc, wherever required, if feasible, for inspection of work at required locations with essential safety features for the workmen etc., complete as per directions and approval of Engineer-in-charge. Note:- (1) The elevational area of the scaffolding shall be measured for payment purpose. (2) The payment will be made once only for execution of all items for such works.
DSR rate₹338.25as per item analysis
Item code
24.2
Sub-head
SH 24 · CONSERVATION
Unit
See analysis
Source row
26
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for area 22.5x9.0=202.50 sqm
MATERIAL
Assuming shuttering material will become unserviceable after use of 40 times Adding for maintenance @ 10% of cost
Taking slvage value after full use of material @ 25% of cost
7397
Base jack
each
0.3
₹155.00
₹46.50
Qty taken for cost of using once =14x0.85/40=0.2975
4009
Mild steel tubes hot finished welded type
kilogram
80.02
₹72.00
₹5,761.44
Vertical standard 2.5m length=7x2x9x2.5=315.00 m
Side support 6.00m length=3x2x6.00=36.00m
Horizonatal support 3.00mlength=18x3x3.00=162.00m
Total=1026.00m
@ 3.67 kg/m =3765.42 kgQty taken for
7387
Spigot for standard jointing
kg
2.63
₹44.00
₹115.72
7x2x9=126 nos x 0.40m length = 50.40m @2.46kg /m=123.98kgQty taken for cost of using once= 123.98x0.85/40=2.63kg
1034
Bolts and nuts upto 300 mm in length
quintal
0.008
₹5,200.00
₹41.60
2x7x2x9=252 nos @ 0.15 kg each=37.80 kg =0.378qQty taken for cost of using once= 0.378x0.85/40=0.008q
7346
Double coupler
each
2.55
₹49.00
₹124.95
Clamp coupler for fixing MS tube with scafolding 2x3x2+2x18x3=120 nosQty taken for cost of using once= 120x0.85/40=2.55 nos
7398
Challies
each
1.91
₹834.00
₹1,592.94
3 nos x 18 lines=54 nosTwo level plate challies=2x18 lines=36nosTotal=90 nos
Qty taken for cost of using once=90x0.85/40=1.9125 nos
7399
Cup lock
each
27.92
₹50.00
₹1,396.00
For Vertical standards=(5x7x2x9=630 nos) +(2x18x19=694 nos)Total=1314 nos
Qty taken for cost of using once= 1314x0.85/40=27.92
2205
Carriage of Steel
tonne
6.054
₹0.00
₹0.00
40mm dia MS pipe=3765.42kg
25mm spigot=123.98kgNuts &
bolts=37.80kgclamp=120 nos@1.00kg
each=120.00kgChallies=90 nos @ 15.00kg
each=1350.00kgCup locks=1314 nos @
0.50kg each=
657.00kgTotal=6054.20kg=6.054 tonne
LABOUR
0116
Fitter (grade 1)
day
15.5
₹897.00
₹13,903.50
0114
Beldar
day
31
₹736.00
₹22,816.00
9999
Sundries
L.S.
1,035
₹2.27
₹2,349.45
Rate build-up
cost of using once= 3765.42x0.85/40=80.02kg
—
TOTAL
₹48,148.10
Add 1 % Water charges on "W"
₹481.48
TOTAL
₹48,629.58
Add GST on "X" (multiplying factor 0.2127)
₹10,343.51
TOTAL
₹58,973.09
Add 15% CPOH on "Y"
₹8,845.96
TOTAL
₹67,819.05
Add Cess @ 1% on "Z"
₹678.19
Cost of 202.50 sqm
₹68,497.24
Cost of 1.00 sqm
₹338.26
Say
₹338.25
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.