DSR 2023 · SH 24 · CONSERVATION

CPWD DSR item 24.1 rate analysis

Raking out joints of stone masonry surface to the required width and depth, with due care and precaution, by mechanical / manual means, including preparing and cleaning the surface for re-pointing/ refilling of joints, including disposal of rubbish to the dumping ground within 50 metre lead.

Published rate₹72.45DSR 2023
Rate analysis

Raking out joints of stone masonry surface to the required width and depth, with due care and precaution, by mechanical / manual means, including preparing and cleaning the surface for re-pointing/ refilling of joints, including disposal of rubbish to the dumping ground within 50 metre lead.

DSR rate₹72.45as per item analysis
Item code
24.1
Sub-head
SH 24 · CONSERVATION
Unit
See analysis
Source row
6

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
LABOUR
0114 Beldar day 0.53 ₹736.00 ₹390.08
0115 Coolie day 0.08 ₹736.00 ₹58.88
0101 Bhisti day 0.07 ₹816.00 ₹57.12
9999 Sundries L.S. 1.43 ₹2.27 ₹3.25

Rate build-up

TOTAL ₹509.33
Add 1 % Water charges on "W" ₹5.09
TOTAL ₹514.42
Add GST on "X" (multiplying factor 0.2127) ₹109.42
TOTAL ₹623.84
Add 15% CPOH on "Y" ₹93.58
TOTAL ₹717.42
Add Cess @ 1% on "Z" ₹7.17
Cost of 10.00 sqm ₹724.59
Cost of 1.00 sqm ₹72.46
Say ₹72.45

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook