Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge.
150 mm nominal size dia
Published rate₹2,102.25per metre
Rate analysis
Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge.
DSR rate₹2,102.25per metre
150 mm nominal size dia
Item code
23.11.2
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
metre
Source row
687
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 30 metre
MATERIAL
7743
M.S. pipe 150 mm dia casing pipe
metre
30
₹1,250.00
₹37,500.00
7765
M.S. socket 150 mm dia
each
5
₹225.00
₹1,125.00
9999
Extra for making slots
L.S.
1,208.05
₹2.27
₹2,742.27
2344
Carriage of cast iron pipes 150 mm dia
100 metre
0.3
₹0.00
₹0.00
including loading and unloading Painting with anticorrosive Paint 3.14 x.160x30.00=15.07 sqm.
13.65.1
Rate as per Item No.13.65.1 of SH:Finishing
sqm
15.07
₹140.25
₹2,113.57
LABOUR
0114
Beldar
day
1.4
₹736.00
₹1,030.40
0130
Mistry
day
0.5
₹897.00
₹448.50
Rate build-up
TOTAL
₹44,959.74
Add 1 % Water charges on "W-A"
₹428.46
TOTAL
₹45,388.20
Add GST on "X-A" (multiplying factor 0.2127)
₹9,204.51
TOTAL
₹54,592.71
Add 15% CPOH on "Y-A"
₹7,871.87
TOTAL
₹62,464.58
Add Cess @ 1% on "Z-A"
₹603.51
Cost for 30 metre
₹63,068.09
Cost of 1 metre
₹2,102.27
Say
₹2,102.25
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.