DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.1.1 rate analysis

Providing and laying integral cement based treatment for water proofing on horizontal surface at all depth below ground level for under ground structures as directed by Engineer-in-Charge and consisting of : (i) Ist layer of 22 mm to 25 mm thick approved and specified rough stone slab over a 25 mm thick base of cement mortar 1:3 (1 cement : 3 coarse sand) including applying of twice ( at base and top of mortar ) cement slurry @ 2.2kg/m2 (each time) mixed with water proofing compound conforming to IS:2645 in the recommended proportion over the leveling course (leveling course to be paid separately). Joints sealed and grouted with cement slurry mixed with water proofing compound. (ii) 2nd layer of 25 mm thick cement mortar 1:3 (1 cement: 3 coarse sand) mixed with water proofing compound in recommended proportions. (iii) Finishing top with stone aggregate of 10 mm to 12 mm nominal size spreading @ 8 cudm/sqm thoroughly embedded in the 2nd layer. Using rough kota stone.

Published rate₹1,515.60DSR 2023
Rate analysis

Providing and laying integral cement based treatment for water proofing on horizontal surface at all depth below ground level for under ground structures as directed by Engineer-in-Charge and consisting of : (i) Ist layer of 22 mm to 25 mm thick approved and specified rough stone slab over a 25 mm thick base of cement mortar 1:3 (1 cement : 3 coarse sand) including applying of twice ( at base and top of mortar ) cement slurry @ 2.2kg/m2 (each time) mixed with water proofing compound conforming to IS:2645 in the recommended proportion over the leveling course (leveling course to be paid separately). Joints sealed and grouted with cement slurry mixed with water proofing compound. (ii) 2nd layer of 25 mm thick cement mortar 1:3 (1 cement: 3 coarse sand) mixed with water proofing compound in recommended proportions. (iii) Finishing top with stone aggregate of 10 mm to 12 mm nominal size spreading @ 8 cudm/sqm thoroughly embedded in the 2nd layer.

DSR rate₹1,515.60as per item analysis

Using rough kota stone.

Item code
22.1.1
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
4

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10.00 sqm
MATERIAL
Ist layer
Cement mortar 1:3 for fixing of stone 10x0.025 = 0.25 cum
3.8 Rate as per Item Number 3.8 of SH: MORTARS cum 0.25 ₹4,881.95 ₹1,220.49
Kota stone slab = 10 sqm
Wastage @ 10% = 1 sqm
Total = 11 sqm
1169 Kotastone slab 25mm thick (rough cheseled) sqm 11 ₹280.00 ₹3,080.00
Cartage 11x0.025 @ 2330 kg/m3 = 0.64 t
2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 0.64 ₹0.00 ₹0.00
Cement mortar 1:3
10x0.025 = 0.25 cum
Wastage @ 12% = 0.03 cum
Total = 0.28 cum
3.8 Rate as per Item No.3.8 of SH: MORTARS cum 0.28 ₹4,881.95 ₹1,366.95
for slurry Bed
2x10.00 @ 2.20kg/m2 = 44.00 kg
Joints
4x3.7x0.02x0.025 = 0.0074 cum
25x0.56x0.02x0.025 = 0.0070 cum
Total= 0.0144 cum @ 1440 kg/cum=20.74 kg
Total = 64.74 kg or 0.065 tonne
0367 Portland Cement (OPC-43 grade) tonne 0.065 ₹5,156.00 ₹335.14
2209 Carriage of Cement tonne 0.065 ₹0.00 ₹0.00
Mortar = 0.25 + 0.28 = 0.53 cum
Cement in 0.53 cum @ 5.1 q/cum = 2.7 quintal
Cement in slurry = 0.65 quintal
Total = 3.35 quintal =6.70 bags of 50 kg of cement
1213 Water proofing materials@0.10 kg per 50 kg of cement used kilogram 0.67 ₹45.00 ₹30.15
0296 Stone Aggregate (Single size) : 12.5 mm nominal size cum 0.08 ₹1,400.00 ₹112.00
spreadig@ 8 cudm/sqm= 1x10x8x1/1000 = 0.08 cum
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.08 ₹0.00 ₹0.00
Labour for base mortar & kota stone laying i/c slurry job
0125 Mason (for plain stone work) 2nd class day 1.2 ₹816.00 ₹979.20
0114 Beldar day 1 ₹736.00 ₹736.00
0115 Coolie day 1 ₹736.00 ₹736.00
LABOUR
Labour for top layer & spreading stone grit
0125 Mason (for plain stone work) 2nd class day 1.08 ₹816.00 ₹881.28
0114 Beldar day 1.08 ₹736.00 ₹794.88
0101 Bhisti day 0.45 ₹816.00 ₹367.20
9999 Sundries L.S. 6.24 ₹2.27 ₹14.16

Rate build-up

TOTAL ₹10,653.45
Add 1 % Water charges on "W" ₹106.53
TOTAL ₹10,759.98
Add GST on "X" (multiplying factor 0.2127) ₹2,288.65
TOTAL ₹13,048.63
Add 15% CPOH on "Y" ₹1,957.29
TOTAL ₹15,005.92
Add Cess @ 1% on "Z" ₹150.06
Cost for 10.00 sqm ₹15,155.98
Cost for 1 sqm ₹1,515.60
Say ₹1,515.60

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.